Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | Working on a schedule for participation of the browser testing of the 6.4 LexEVS API. Anticipating getting a release in February that will include the search extensions. |
Report Writer |
|
Term Browser | Currently working on the 2.8 release development. Specifically improving the graph display for larger graphs. Putting in a ticket for an AppScan on DEV to make sure the updates have not caused any vulnerabilities. |
Term Suggestion Application | |
NCIm Browser | |
Triple Store Prototype | Working on the deployment of a Triple Store prototype using Apache Jena. Hope to have it deployed to the NCI environment by the end of this week. |
JIRA Issues
Issue Number | Description | Status |
---|---|---|
NCITERM-704 | Improve display of large graphs. | Completed the development of the GraphReductionUtils class. The utility class automatically reduces a large graph by aggregating nodes with the same inbound or outbound role or association and same source or target concept into a group node. The user would be able to click on the aggregated node to view the name of code of each member node (i.e., concept). Started integration of GraphReductionUtils with the existing graph code component code. |
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
Term Browser 2.8 Release | Continue development of the 2.8 Term Browser release. |
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
7/17/2014 | Deployment of software, even small upgrades, have been a lengthy process. | This especially affects smaller releases in which there are security or bug fixes. | The Agile practices migration have been put on hold for now. | ||
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||