Attendees

NameRole
  
  
  

 

Action Items

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
      .

Progress

Area of InterestDetails
LexEVS 6.3

The systems team is requested that the DEV environment AHP setup to be completed before they will configure the QA environment.  We put in a ticket on Tuesday and it is currently being worked on.

Report Writer

Need a decision on where this functionality is going to go to start creating trackers and scope document.

Term Browser 

Continued testing of the 6.3 release with the Term Browser.  Starting development of the 2.7 release starting with the automated test trackers.

Added a new scope item for improving performance of the AppScan of the Term Browser following the failed attempt to run an AppScan on the DEV tier.  We will work with the Security lead and systems team to setup monitors to see where the AppScan is failing and why it is failing.

Meta Download Validation App

Term Suggestion Form

 

NCIm Browser

 

JIRA Issues

Issue NumberDescriptionStatus
NCITERM-669View in Hierarchy - Sibling concepts showing up twice.

The JSON string returned by the API places the focus node at front (as the first child node of its parent node) instead of returning child nodes alphabetically. Will track and remove the redundant focus node from the child node list.

NCITERM-668PDQ Definitions not correctly formatted.

Resolved the underlying issue.

 

NCITERM-660UI Testing Utility.

Developed a RelationshipUtils for generating data required for populating the relationship tab.

Identified a method for improving the performance of the relationship tab.

   

Schedule Changes

 

#DescriptionDue DateResourcesNotesRisksMitigation
       

 Planned Activities

Area of InterestDetails
Report WriterDevelop Project plan for 2.1 release.
Term Browser 2.7 ReleaseScheduling the release and start development.

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
 04/10/14 Deployments have been taking long periods of time. There is a lot of overhead getting through the itersH H Speaking with members of the QA team to find ways to streamline the testing/deployment processFinding ways to better integrate the development and QA team. Spoke to EVS Tools TPM requesting the correct communication channels.
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
 7/17/2014Deployment of software, even small upgrades, have been a lengthy process.This especially affects smaller releases in which there are security or bug fixes. The Agile practices migration have been put on hold for now.
 09/10/2014Getting the environment in place for the Mayo trip to NCI.Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd.  We are currently one week behind.  The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. Currently we only have the DEV environment setup for the LexEVS API>
      

Dependencies

Opened DateDescriptionAssigned
 .
 
   
   