Attendees

NameRole
  
  
  

 

Action Items

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
      .

Progress

Area of InterestDetails
LexEVS 6.3

The CTS2 AppScan was completed on QA. Deployment to production completed.

Put in a ticket to have the 6.0, 6.1 URLs repointed to the 6.3 container. 

Report Writer

Need a decision on where this functionality is going to go to start creating trackers and scope document.

Term Browser 

Provided an updated automated testing app to the QA team.  They were able to run through all the automated tests in around 3 hours.

Implemented a new view graph functionality to replace the NCBO implementation.  Reviewed it with the EVS group and it was agreed to proceed with current implementation and build from there.

The DEV AppScan to test the updates Kim made to handle specific vulnerabilities was kicked off.  Still were seeing some slow performance on the AppScan but the security team has made some configuration changes that we hope will speed things up.  AppScan is currently at 15% complete.

Meta Download Validation App

Term Suggestion Form

 

NCIm Browser

 Evaluated the effort of expanding the automated test application to the NCIm Browser.  Effort for the NCIm browser should be considerably less than Term Browser.

JIRA Issues

Issue NumberDescriptionStatus
NCITERM-685Graph Widget implementation.

Implemented a view graph link to allow the user to view the distance one relationships by type or all at once.

Added zoom in/out and move up/down/left/right features.

Schedule Changes

 

#DescriptionDue DateResourcesNotesRisksMitigation
       

 Planned Activities

Area of InterestDetails
Term Browser 2.7 ReleaseContinue development of the 2.7 release.

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
 04/10/14 Deployments have been taking long periods of time. There is a lot of overhead getting through the itersH H Speaking with members of the QA team to find ways to streamline the testing/deployment processFinding ways to better integrate the development and QA team. Spoke to EVS Tools TPM requesting the correct communication channels.
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
 7/17/2014Deployment of software, even small upgrades, have been a lengthy process.This especially affects smaller releases in which there are security or bug fixes. The Agile practices migration have been put on hold for now.
 09/10/2014Getting the environment in place for the Mayo trip to NCI.Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd.  We are currently one week behind.  The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. Currently we only have the DEV environment setup for the LexEVS API>
      

Dependencies

Opened DateDescriptionAssigned
 .
 
   
   