Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | The systems team shutdown the 6.0, 6.1 and 6.2 containers with all the URL's now pointing to the 6.3 container. Leaving the 5.1 production and stage container up. Stage will be shutdown when the latest data is deployed. |
Report Writer | Need a decision on where this functionality is going to go to start creating trackers and scope document. |
Term Browser | AppScan completed in 5 days with 3 cross site scripting vulnerabilities. Continuing QA testing. QA Team opened a couple of tickets, one of which was already fixed by Kim (partonomy tree). Having issue with the back button sporadically on Term Browser |
Meta Download Validation App | |
NCIm Browser | Working on Scope Document and PTE for NCIm browser 2.6 release. |
JIRA Issues
Issue Number | Description | Status |
---|---|---|
NCITERM-691 | View In Hierarchy tree node expand/collapse issue. | Resolved a tree node expansion issue. Improved tree node expansion performance. |
NCIM-207 | Migrate to LexEVSAPI 6.3. | Identified the difference between metabrowser v2.5 and LexEVSAPI 6.3 library folders. Removed eclipse jars, protégé.jar and protege-owl.jar from v2.6 library folder. |
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
Term Browser 2.7 Release | Test and deployment of the 2.7 release. |
NCIm Browser 2.6 Release | Planning for development of 2.6 release. |
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
7/17/2014 | Deployment of software, even small upgrades, have been a lengthy process. | This especially affects smaller releases in which there are security or bug fixes. | The Agile practices migration have been put on hold for now. | ||
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||