Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | The 6.4 API has been deployed to QA. Testing starting now. |
Report Writer | We are making progress on the report writer UI and would like to meet with the operations group and a couple of editors that use report writer to discuss what is currently there and what else is needed for the initial release. |
Term Browser | Provided a release candidate tag for the Term Browser 2.9 release to the QA team. |
Term Suggestion Application | Provided a release candidate tag for the Term Suggestion 2.4.1 release to the QA team. |
NCIm Browser | Provided a release candidate tag for Metathesaurus Browser 2.7 release. |
Triple Store Prototype | SPARQL server evaluation support.
|
Biomarkers Support | Assessed performance of the name search with a restriction on biomarker related terms (e.g., EGFR Gene and EGFR NP_005219.2:p.L858R). |
JIRA Issues
Issue Number | Description | Status |
---|---|---|
TERMFORM-75 | Updates to UI per the new NCI branding guidelines. | Implemented. |
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
Term Browser 2.9 Release | Continue development of the 2.9 Term Browser release. |
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
7/17/2014 | Deployment of software, even small upgrades, have been a lengthy process. | This especially affects smaller releases in which there are security or bug fixes. | The Agile practices migration have been put on hold for now. | ||
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||