NIH | National Cancer Institute | NCI Wiki  

Attendees

NameRole
  
  
  

 

Action Items

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
      .

Progress

Area of InterestDetails
LexEVS 6.3

After reviewing the usage statistics it was decided that we should shutdown the old 5.1services on September 18th permanently. 

Need to put in a ticket for redirecting the 6.0 and 6.1 URL's to the 6.3 server on the DEV and QA tiers.  Tracy will put in a ticket for this.

Report Writer

Need a decision on where this functionality is going to go to start creating trackers and scope document.

Term Browser 

The AppScan had to be restarted and we are now at 13% complete.  If this is right then it will take 7 days to complete the scan.

With a number of completed high priority bug fixes done we are going to proceed with the 2.7 release even though we have completely figures out the AppScan performance issue yet.

Meta Download Validation App

Term Suggestion Form

SSL has been applied to the Term Suggestion application on DEV. 

NCIm Browser

SSL has been applied to the Metathesaurus browser on DEV.

Put in ticket to fix the URL issue with Metathesaurus browser to Term Browser on the NCIm home page.  The url was missing the /ncitbrowser/ extension which was causing an error.

JIRA Issues

Issue NumberDescriptionStatus
NCITERM-670Term Browser AppScan Performance.

Continue monitoring the status of appscan.

NCITERM-688Partonomy Tree.

Completed the initial capability design on visualization of locality and path-to-roots in a partonomy based on a collection of part-of and has-part relationships as defined in supported associations of some coding schemes.

Schedule Changes

 

#DescriptionDue DateResourcesNotesRisksMitigation
       

 Planned Activities

Area of InterestDetails
Term Browser 2.7 ReleaseContinue development of the 2.7 release.

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
 04/10/14 Deployments have been taking long periods of time. There is a lot of overhead getting through the itersH H Speaking with members of the QA team to find ways to streamline the testing/deployment processFinding ways to better integrate the development and QA team. Spoke to EVS Tools TPM requesting the correct communication channels.
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
 7/17/2014Deployment of software, even small upgrades, have been a lengthy process.This especially affects smaller releases in which there are security or bug fixes. The Agile practices migration have been put on hold for now.
 09/10/2014Getting the environment in place for the Mayo trip to NCI.Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd.  We are currently one week behind.  The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. Currently we only have the DEV environment setup for the LexEVS API>
      

Dependencies

Opened DateDescriptionAssigned
 .
 
   
   
  • No labels