Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | Entered a ticket to create a VM that images the current DEV environment to be used while the CentOS and Java 8 upgrades. |
Report Writer |
|
Term Browser | Continue to explore potential causes for the resolved value set coding scheme entity count issue. Provided technical support to the Operations team to repair all broken SPARQL queries contained in the following two XML files:
|
Term Suggestion Application | |
NCIm Browser | Working on an issue with the DataQA deployment of the 2.7 release of the Metathesaurus Browser. I believe the AHP track was not created correctly so currently working with SCM team to get the issue resolved. |
Triple Store Prototype |
|
Biomarkers Support | Follow up meeting with the CTRP group was held on Monday. Awaiting direction on updates to the prototype from that discussion. |
Neoplasm Core | |
Other Support |
JIRA Issues
Issue Number | Description | Status |
---|---|---|
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
Term Browser 2.9 Release | Continue development of the 2.9 Term Browser release. |
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
7/17/2014 | Deployment of software, even small upgrades, have been a lengthy process. | This especially affects smaller releases in which there are security or bug fixes. | The Agile practices migration have been put on hold for now. | ||
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||