NIH | National Cancer Institute | NCI Wiki  

Attendees

NameRole
  
  
  

 

Action Items

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
      .

Progress

Area of InterestDetails
LexEVSEntered a ticket to create a VM that images the current DEV environment to be used while the CentOS and Java 8 upgrades.  Systems team said work on this tickets should happen within the next couple of days.
Report Writer

 

Term Browser 

AppScan passed with no vulnerabilities.  QA Team is currently working on test results report to move to stage and production.

Constructed a method for removing relationship data from an OWL Class. 

Reviewed LexEVS JIRA Backlog for Tree Service related items.

Provided SPARQL prototype source code to the Operations Team.

Reviewed OWL2 formatted NCI Thesaurus.

Term Suggestion Application 
NCIm Browser 
Triple Store Prototype

Modified SPARQL queries used in the SPARQL prototype in supporting the testing conducted by the Operations team on NCI triple-store servers (Note: the NCI triple-store servers are hosting the OWL2 formatted NCI Thesaurus.)

Biomarkers Support

Awaiting direction on updates to the prototype from that discussion.

Neoplasm Core

 

Other Support 

JIRA Issues

Issue NumberDescriptionStatus
   
   
   

Schedule Changes

 

#DescriptionDue DateResourcesNotesRisksMitigation
       
  •  Planned Activities

Area of InterestDetails
NCIm and Report Writer releaseDeveloping a new release of NCIm browser for a Chrome issue and Report writer to make compatible with the latest LexEVS API.
  

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
 09/10/2015  H H AppScan are taking long periods of time to complete.  For Term browser, the minimum has been 5 days.We are working on both the code base and configuration of the scan to try to improve performance.  We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required.
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
 7/17/2014Deployment of software, even small upgrades, have been a lengthy process.This especially affects smaller releases in which there are security or bug fixes. The Agile practices migration have been put on hold for now.
 09/10/2014Getting the environment in place for the Mayo trip to NCI.Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd.  We are currently one week behind.  The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. Currently we only have the DEV environment setup for the LexEVS API>
      

Dependencies

Opened DateDescriptionAssigned
 .
 
   
   
  • No labels