Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | |
Report Writer | Produced various cancer staging reports.
Created a new tag, v2.7-beta.1, for testing Java-8 migration and the replacement of the legacy caCORE Common Security Module (CSM) by the apache shiro security framework for supporting authentication, authorization, cryptography, and session management. |
Term Browser | Still waiting for the QA environment to be setup to continue deployment. |
NCIm Browser | Still waiting for the QA environment to be setup to continue deployment. |
Term Suggestion Application | Waiting for deployment of the new tag to the new blade server for testing. |
Triple Store Prototype | Had the meeting with the group about the SPARQL report writer on Monday. Received a few additional requirements. |
Biomarkers Support |
|
Neoplasm Core |
|
Other Support |
|
JIRA Issues
Issue Number | Description | Status |
---|---|---|
EVSREPORT-105 | JAVA 8 Upgrade | Rebuilt neopl-core.jar for generating the neoplasm core package. |
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||