Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | Performed preliminary testing on Mayo’s new value set hierarchy implementation using lexbig-6.5.1.SNAPSHOT.1.jar. The results indicate that the API may not work through the remote API. Informed Mayo of the findings. |
Report Writer | Performed trouble-shooting on a source combo-box not being populated issue reported by the Operations team. reported by the Operations team. |
Term Browser | Put in request to point the live URL to the latest release of the browsers/server. Update - system team is still working on it. |
NCIm Browser | Put in request to point the live URL to the latest release of the browsers/server. Update - system team is still working on it. |
Term Suggestion Application | Put in request to point the live URL to the latest release of the browsers/server. Update - system team is still working on it. |
EVS REST API | Developed SPARQL queries for searching presentation type (i.e., names) and other annotation properties using case-insensitive exactMatch, startsWith, endsWith, and contains algorithms. Explored the Levenshtein algorithm for assigning a goodness of match measurement to matched concepts. |
Biomarkers Support |
|
Neoplasm Core |
|
Other Support |
|
JIRA Issues
Issue Number | Description | Status |
---|---|---|
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||