Attendees
Name | Role |
---|---|
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
. |
Progress
Area of Interest | Details |
---|---|
LexEVS | |
Report Writer | Continuing development on the java 8 applications including the report writer. Removed the CSM component. |
Term Browser | Deployed the 2.11 release to the new DEV blade server. |
NCIm Browser | Deployed the 2.9 release to the new DEV blade server. |
Term Suggestion Application | |
Triple Store Prototype | Scheduled the meeting for the SPARQL Report Writer to review the functionality. |
Biomarkers Support | Awaiting direction on updates to the prototype from that discussion. |
Neoplasm Core |
|
Other Support |
JIRA Issues
Issue Number | Description | Status |
---|---|---|
EVSREPORT-106 | Hibernate Configuration File External Dependency. | Used SourceForge DTD URL with SYSTEM in hibernate.cfg.xml. |
EVSREPORT-105 | JAVA 8 Upgrade | Updated jars in the browser libs to make them compatible to LexEVS6.5.0.
Updated application_client_config-remote.xml. Modified project.properties. Modified application_config.xml. |
EVSREPORT-107] | Remove CSM Dependency. | Replaced CSM by Apache Shiro for authentication and authorization. Modified the build script. |
Schedule Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
Planned Activities
Area of Interest | Details |
---|---|
NCIm and Report Writer release | Developing a new release of NCIm browser for a Chrome issue and Report writer to make compatible with the latest LexEVS API. |
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
09/10/2015 | H | H | AppScan are taking long periods of time to complete. For Term browser, the minimum has been 5 days. | We are working on both the code base and configuration of the scan to try to improve performance. We are also looking at open source code scanners that could possibly be used ahead of the AppScan to at least limit the number appscans required. | ||||
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
7/17/2014 | Deployment of software, even small upgrades, have been a lengthy process. | This especially affects smaller releases in which there are security or bug fixes. | The Agile practices migration have been put on hold for now. | ||
09/10/2014 | Getting the environment in place for the Mayo trip to NCI. | Need to get each of the environment (DEV,QA,Stage) in place before the Mayo trip on September 22nd. We are currently one week behind. The impact is that the Mayo developer will be onsite to work on the deployments and the tiers will not be in place. | Currently we only have the DEV environment setup for the LexEVS API> | ||
Dependencies
Opened Date | Description | Assigned |
---|---|---|
. | ||