# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
64 | Scott | To follow up on URI's on OWL2 with Harold. | on hold | |||
156 | Scott | Scott to work with Gilberto to determine what is needed for OWL 2 requirements | 2014.04.30 | on hold | ||
164 | Cory | Cory to add implementation to CTS2 implementations page. | 2014.04.30 | on hold | ||
170 | Scott | Update the ARC dates to include range of dates for each tier. | 2014.05.14 | on hold | ||
185 | Gilberto | Create Jira for OWL 2 Annotation issue in the API. | 2014.05.28 | open | ||
197 | Scott | Do a gap analysis on what the URI_Resolver logs and what NCI would like to know from these logs | 2014.6.18 | on hold | ||
200 | Larry/Sherry | Query current LexEVS users about use of SOAP, REST or QBE services in the legacy caCORE api's | 2014.6.18 | open | ||
204 | Larry | Plan for August NLM Demo/Meeting. | 2014.07.09 | open | ||
205 | Scott | See if URI's are case senstitive sensitive as handled by the URI resolvers | 2014.07.16 | open | ||
206 | Scott | Determine if CTS2 supports a distinction between transitive derived relationships and structural graphs | 2014.07.23 | open |
Progress
Immediate Priorities and Problems (Mayo Team) | Scott: Loader testing against, MetaBrowser Update, PTE
Cory: Working JIRA #'s 371, 538
Craig: Project Plan Updates, NLM Demo Meeting, September F2F
|
| |
caDSR and Value Set and other URIs (Weekly Status) | Scott started to look at case-sensitivity for URI Resolver. For now, no further investigation. For now, URIs will be in lower case. | ||
Dev DRT request | SSH connection - resolved and Scott can log on. Scott was able to look at the system. Nothing is started - Scott will send Jacob a version of the PTE today. Jacob will get the server up and running (with help of Scott). | ||
Test Plan and checklist for moving from Dev to QA | Need to Identify responsibility for creating the test plan and associated dates. QA will do the test plan. A different test plan template will be created for Agile. This will be part of the Agile process. Up front work can be done in order to help with this process. | ||
Plans for the future of caCORE webservices. | Perhaps leave this in for this iteration. This would require additional testing. Also, not sure of usage (external) - there is no certainty on who is using. No action required for this release. To be revisited in 6.3. | ||
Discussion of JIRA #597 | CTS2 Association Graph: Proposed as a CTS2 Specification implementation. Given the current timeline, we will postpone this item - move to 6.3. Scott to look at question from Gilberto in the Jira Item and provide comment as to how implementation could be done. | ||
Agile discussion | Agile Team Structure - NCI and Mayo teams and the roles associated to each team in order to support Agile.
|
...