Phase | Date | Milestones | Deliverables |
---|---|---|---|
Inception | 4/1/2010 (month 1) | KnowledgeRS:Project Management Plan | |
Elaboration | 5/1/2010 (month 2) | v0 PIM, scope document | Monthly Status Report |
| 6/1/2010 (month 3) | final CGSS, use cases, requirements matrix | Monthly Status Report |
| 7/1/2010 (month 4) | final PIM, scope document | Monthly Status Report
|
Construction | 8/1/2010 (month 5) | v1 PSM | Monthly Status Report |
| 9/1/2010 (month 6) | v2 PSM | Monthly Status Report |
| 10/1/2010 (month 7) | final PSM | Monthly Status Report |
| 11/1/2010 (month 8) | v3 MDR, Model, and KM reference implementations | Monthly Status Report |
| 12/1/2010 (month 9) | final MDR, Model, and KM reference implementations | Monthly Status Report |
| 1/1/2011 (month 10) | bug fixes | Monthly Status Report |
| 2/1/2011 (month 11) | candidate release MDR, Model, and KM reference implementations | Monthly Status Report |
Transition | 3/1/2011 (month 12) | final release | Monthly Status Report |
Artifacts
Deliverable | Artifacts | 4/10 | 5/10 | 6/10 | 7/10 | 8/10 | 9/10 | 10/10 | 11/10 | 12/10 | 1/11 | 2/11 | 3/11 | ||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
| ||||||||||
| Management Plan |
|
|
|
|
|
|
|
|
|
| Final | |||||||
| WBS |
|
|
|
|
|
|
|
|
|
| Final | |||||||
| Project Plan |
|
|
|
|
|
|
|
|
|
| Final | |||||||
Software Code Base |
| Draft | Draft | Draft | Draft | Draft | Draft | Draft | Draft | Draft | RC | Final | |||||||
Monthly Status Report |
| Emailed | Report | Report | Report | Report | Report | Report | Report | Report | Report | Report | Report | ||||||
Draft Design Review Package |
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final | |||||||
Test Package |
|
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final | ||||||
Test Plan |
|
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final | ||||||
Test Report |
|
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final | ||||||
ECCF Documentation |
|
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final | ||||||
caBIG Compatibility Package |
|
|
|
| Draft |
|
|
| Revised |
|
| Final | |||||||
Deployment Package |
|
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final | ||||||
Installation Package |
|
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final | ||||||
Release Notes |
|
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final | ||||||
Installation Guide |
|
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final | ||||||
Software Product Documentation |
|
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final | ||||||
BDA Compliance Package |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
BDA Compliance Matrix |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
BDA Feedback Report |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
Product Install QA Report |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
BDA Software Test Plan and Scenarios |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
BDA Software Test Results |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
BDA Software Code |
|
|
|
|
|
|
|
| Draft |
|
| Revised | Final | ||||||
Section 508 Compliance Package |
|
|
|
|
|
|
|
|
|
|
| Draft | Final |