# | Assigned | Description | Date Identified | Due Date | Date Completed | Comments | Status |
---|---|---|---|---|---|---|---|
1 | Kumar | Submit Mod to contracts for cost extension | 9/15/2014 | 11/14/2014 | 2/18/2015 | 9/18/2014: Completed mod document; need clarification on scope from stakeholders; will address it during status meeting. 10/3/2014: Mod with contracts, awaiting execution 10/7/2014: Mod with vendor for providing proposal 10/16/2014: Received proposal and being reviewed 10/23/2014: Mod on hold until details of adding Stanford resources are worked out 2/18/2015: Initial mod to be executed to continue work as bringing Stanford on board will take time. This is being tracked on another action item. | ClosedIn Progress |
2 | Kumar Kuntipuram | Update SOW with new tasks and submit for mod | 1/8/2015 | 1/14/2015: Received additional task information and corresponding personals for the mod. Currently being evaluated 1/28/2015: Started work on mod documents | In Progress | ||
3 | JJ, Kumar | Verify status of production tech stack upgrade | 1/8/2015 | 1/28/2015: Awaiting systems to update server | Open | ||
4 | Kumar Kuntipuram | Work with QA and dev to explore possibilities of automation and CI for Protégé. | 2/5/2015 | 2/12/2015: Provided QA with Protégé application to run and familiarize. QA also exploring tools for desktop application automation. | In Progress |
...