What went well
Description | Author |
---|---|
Neo4j technical research and DevOps went well | Amit |
Get clarity with point system | Dimitri |
The sprint was well planned. | Ming |
Data have been successfully loaded. Data transformation worked well. | Kevin |
Have all the information needed to carry out my tasks. | Yizhen |
Good team work that helped clear potential risks to the project | Ajay |
Good to have wireframe and also FE team was very help to visualize the project | Ann |
Scrums have been going well, short and concise. Key information is shared. | Mark |
Team came together nicely | Ye/Pihl |
What could have gone better?
Description | Author |
---|---|
No proper designated space to manage team documents | Mark/Amit |
No road map for data milestones, so couldn't map exactly to the FE pages | Amit/Dimitri/Mark |
More communication between FE and BE so team can understand each other better | Ming/Yizhen |
Tickets need to be broken down better and need to be documented better | Phil/Ye |
Need road map for all components to plan for QA activities | Ann/Mark |
Hard to map tickets in each sprint to QA activities | Ann |
Data loading tasks were not planned well. | Mark |