Project | Goal | Assigned to | Accomplished? | |
---|---|---|---|---|
1 | ICDC | Complete the following ICDC prototype views: Dash board view, Study, Study detailed, Case, Case detailed, Program and Program detailed views. | Dimitri/Ajay | Wireframes done. Part of dashboard grid, header and footer. Case detailed done. Rest spilling over to next sprint. |
2 | ICDC/CTN | Implement the first integration between front end - back end | Dimitri/Ajay/Yizhen/Ming | Able to do this with short term Fetch command. Plan is to move to Apollo for long-term. |
3 | ICDC/CTN | Load data with integrated Pentaho and Neo4j | Ming | Partially done. Integration research done. Data format btw Pentaho and Neo4J done - not fully integrated. |
4 | ICDC/CTN | Evaluate integration of centralized fence and indexd | Amit/Ye | Partially done - to be finalized Sprint 5. |
5 | ICDC | Confirm with Erika about Google + eraCommon for fence | Matt | Not done. No longer relevant given that Centralized Fence is scheduled to only support iTrust at this time. If this changes, we can re-evaluate Google integration. |
6 | ICDC/CTN | setup newrelic with ICDC dev instances | DevOps | Done. |
7 | ICDC/CTN | refresh neo4j database | DevOps | Done. |
8 | ICDC | setup constraints for NCATS data | Phil | In progress. |
9 | CTN | Performing preliminary review of CTN data | Phil/Todd | Done. |
10 | ICDC/CTN | Establish data ingestion policy | Mark | Done. |
11 | ICDC | Developing first Integration Test Scenarios | QA | Waiting on integration - spillover to next sprint. |
12 | ICDC | 508 compliance testing for Theme Change | QA | Next sprint. |
13 | ICDC | API testing for real data Rest and Graphql endpoint | QA | Done for Rest, GraphQL almost done. |
14 | ICDC/CTN | Complete Neo4J training | All | Done. |
...