SYSTEMS
Systems
  1. Discussion Points:

    • Make sure Mark is included in all systems communications and emails
    • Status of migration on new QA tier.
      • Archive old server - shut down 3/13/23
      • Any complaints?
    • Stage migration status
      • Not yet started - will be done by systems engineering group
        •  Need to find name of personnel doing this work
        •  Email sent today to check on this
    • Semantics URL to be applied to Stage tier for EVS Explorer- handed to Cuong, still open
      • Response received - in progress
    • ncimvn throwing errors on browse. Unable to deploy jars 

      NCI-RITM0428873

    • LexEVS data-qa DB - disk space full - NCI-RITM0429752. Partially resolved but further work needed.

    Decision Points:


LEXEVS UPDATES

LexEVS Sprint Status


  • Snehal has Jira access
    • March reports should proceed normally
    • Will start looking at these next week
    • Add daily activity to User stories being considered
  • Vue3 Updates for Report Exporter nearing completion
  • Working on updating ncitbrowser for Spring 5 - on dev
    • Metathesaurus browser to come
  • LexEVS/CTS2 vulnerability remediation in testing
Future Planning

Discussion Points:

 Planning for Mayo team in the coming fiscal year:

  • Java 8 migration to 11
    • Meeting Thursday 3/23 to discuss with systems
    • EOL Sep '23
      • Corretta Java8 extends through 2026.
    • Waiting for info on migration deadlines
    • Implications for Tomcat containers - Chuck said no likely issues
    • JREs available on servers
      • New VMs will be created to support
Technical Debt remediation

LexEVS Code Debt Refactoring

CTS2 Mapping/URI Resolver

Discussion Points:

Decision Points:

caDSR Query

Discussion Points:

Statistics Dashboard

Discussion Points: 

  • Google analytics - Retiring GA and going to GA4
    • Need further experimentation, documentation
      •  Check for local documentation, post to wiki
    • Per Kim - looks like scripts need to be updated from GA3 to GA4
      • Double check all parties notified
      • EVSExplore
      • NCI Metathesaurus Browser
      • NCI Terms Browser
    • No analytics being collected by EVS Explore
    • Add to Report Exporter and EVS Compare
      • EVS Exporter working - check for ticket
  • Sumo Logic issues

Decision Points:

Comparison/Mapping Tool

Discussion Points:

Decision Points:

EVS transition to virtual machines

Discussion Points:

  • Server Migration 2021
    • QA2
      • QA 1 retirement requested
    • Stage 
      • Instance of VM instantiated. Needs configuration. 
      • Blocker: Waiting to hear from Systems on what is needed to progress, if they have configuration information.
      • Followed by Prod then DataQA
    • Need to improve accountability and communications
      •  Chuck handing off to systems engineering team
      •  Mark to "bird-dog" the handoff
    • Subsumed by Java 11 migration?
      • Discuss with Cuong on 3/23

Decision Points:

Report Exporter
  • Discussion Points:

    • Working on update to Vue3 (JavaScript Framework). EVSREPEXP-451
      • Due: Mar 10 (end of sprint 205); on week 16 of estimated 16
      • master ticket: EVSREPEXP-442 - Migrate Vue.js version from 2.0 to 3.0
      • Description
        • On Dev and being regression tested
          • Addressing items in unit testing
          • Issue with tree display on "Resolve Branch" screen, incorporating new plugin
          • Exporter later feature on Resolve Branch needs tweaking, near completion
    • UA to GA4 migration - already completed
    • Vulnerable dependencies

    Decision Points:

AWS Cloud to be in Separate Account

Discussion Points

  • Frozen

Decision Points:

Team Absences


Mayo Team - Tracy off April 3,4.  Andrew off April 27 - May 1

MSC -

Leidos - 

Systems - 


EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

Discussion Points:

  • Remote API and URI Resolver retirement
    • Looking at 3 months after announcement - July
    • Need an announcement sent out ahead of time
      • Announcement sent out with NCIt release on 3/15/23

Decision Points:


DATA UPDATES
Data

Discussion Points: 

  • Monthlies - complete and on Prod
  • Metathesaurus being processed
  • QA meeting discussed 3/16
    • Script sent to Chao and Eric to detect error in future
    • Further measures that can be taken?

Decision Points:


BROWSER UPDATES

Browser

Discussion Points: 

  • Nothing new this week

Decision Points: 


QA UPDATES

QA

Discussion Points:  (see chart)

  • March data reviewed pn Stage and Prod
  • 1.7 EVS Rest API validated on QA, Stage and Prod

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 

Mark Benson TPM Update

Spreadsheet: EVS Service Tickets.xlsx

...

LexEVS Spring Migration Progress


Technical Debt Related Update

Estimated Effort

Start Date

Complete Date

Status

JIRA

ADO Ticket

Code Inventory4 days12/20/221/30/23Complete
2037998
Lexevs - update "easy" jars2 days1/31/232/13/23Complete
2111723
Update ddlutils - research and design3 days2/2/232/15/23Complete
2122958
Update ddltils - implementations10 days2/15/233/8/23Complete
2141127
Lexevs Unit testing2 days3/8/2023
In ProgressLEXEVS-53252141156
CTS2 lexevs-service vulnerability update2 days3/13/20233/20/23Complete
2141189
CTS2 unit testing2 days3/20/23
In ProgressLEXEVS-53262141198
QA Lexevs / CTS2

3 days




LEXEVS-53272141217
Repair QA issues2 days




Deployment Lexevs / CTS25 days (elapsed)



2141227
Update LexEVS to Java 11 - research and design4 days



2152899
LexEVS Java 11 implementation5 days



2152917
lucene 9 - research and design8 days



2145025
lucene 9 - implementation15 days



2145027
LexEVS Java 11 unit testing3 days



2152921
CTS2 lexevs-service Java 11 - research and design 3 days



2152928
CTS2 lexevs-service Java 11 implementation3 days



2152932
CTS2 unit testing2 days



2152941
QA Lexevs / CTS2

3 days





2152945
Repair QA issues2 days



2153023
Update Jenkins1 day



2152947
Deployment Lexevs / CTS210 days (elapsed)



2152950
lexevs-service-rest-docs vulnerability update design2 days




lexevs-service-rest-docs vulnerability implementation4 days




lexevs-service-rest-docs unit testing1 day




lexevs-service-rest-docs QA

1 day






lexevs-service-rest-docs deployment4 days (elapsed)




lexevs-service-rest-docs Java 11 design

2 days






lexevs-service-rest-docs Java 11 implementation3 days




lexevs-service-rest-docs unit testing1 day




lexevs-service-rest-docs QA

1 day






lexevs-system-test design4 days




lexevs-system-test implementation6 days




lexevs remaining dependency updates - design10 days




lexevs remaining dependency updates - implementation20 days




CTS2 remaining dependency updates - design1 day




CTS2 remaining dependency updates - implementation3 days




Unit testing2 days




QA2 days




Deployment5 days (elapsed)




Total Effort (Approximately)104 days




Technical Debt Related Update

Estimated Effort

Status

Report Exporter vulnerabilities - design4 days
Report Exporter vulnerabilities - implementation5 days
Unit testing2 days
QA2 days
Deployment5 days (elapsed)

...