SYSTEMS
EVS transition to virtual machines

Status:


Stage instabilities fixed by data update.  Ready to proceed

Systems

See ticket chart (above)


LEXEVS UPDATES
Future Planning
  • Complete Report Exporter refactoring and dependency updates

    • (see EVSREPEXP-475 -> 483)

  • Complete all other dependency updates

  • RMI Retirement - in progress

  • Create Report Exporter Roadmap and Gap analysis of functionality and features 

    • Need user session for prioritization and requirements
  • Groom backlog and prioritize existing bugs

LexEVS Sprint Status


Technical Debt remediation

LexEVS Code Debt Refactoring

Report Exporter
    • Discussion Points:

      • Working on update to Vue3 (JavaScript Framework). EVSREPEXP-451
        • master ticket: EVSREPEXP-442 - Migrate Vue.js version from 2.0 to 3.0
        • Description
          • Tickets 486 and 489 on Stage
      • Vulnerable dependencies - in progress (50%)
      • Ticket 487 - digital styling - in progress
      • Feedback form - in progress, waiting for survey approval
Security

Statistics Dashboard

Discussion Points: 

  • Statistics - Sumo Logic
    • Sumo logic will be discontinued
    • Migration scheduled for October
    • Retirement of Sumo in March

Decision Points:

Comparison/Mapping Tool
  • User stories, work on hold for now
AWS Cloud to be in Separate Account

Discussion Points

  • AWS team contacted us about renewing the effort now contract is settled
  • Working to arrange a kick-off meeting - but not getting responses from AWS team

Decision Points:

Team Absences


Mayo Team - Tracy off Sep 4-8, Scott out Aug 18-25

MSC -

Leidos - Mark out Aug 11, Aug22Aug 22-Sep 7

QA -

Gov - Lyubov, August 15-18


EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

Discussion Points:

Decision Points:


DATA UPDATES
Data

Discussion Points: 

Decision Points:


BROWSER UPDATES

Browser

QA UPDATES

QA

Discussion Points: 

  • 1.8 completed on all tiers for RestAPI and EVS Explore
  • 07e on Prod on RestAPI
  • EVS Report Exporter new tag on QA for 2 bug fixes
  • CTS2 patch for vulnerability fix on QA

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 

Mark Benson TPM Update

...

Complete

Technical Debt Related Update

Estimated Effort

Start Date

Complete Date

Status

JIRA

ADO Ticket

Code Inventory4 days12/20/221/30/23Complete2037998
Lexevs - update "easy" jars2 days1/31/232/13/23CompleteLEXEVS-53192111723
Update ddlutils - research and design3 days2/2/232/15/23Complete2122958Update ddltils - implementations10 days2/15/233/8/23Complete2141127Lexevs Unit testing2 days3/8/2023CompleteLEXEVS-53252141156CTS2 lexevs-service vulnerability update2 days3/13/20233/20/23Complete2141189
CTS2 unit testing2 days3/20/234/5/23CompleteLEXEVS-53262141198
QA Lexevs / CTS2

3 days

4/12/2304/24/23CompleteLEXEVS-53272141217
Repair QA issues2 days04/24/2304/24/23Complete
Deployment Lexevs / CTS25 days (elapsed)05/01/2305/03/23CompleteLEXEVS-53282141227
LexEVS Corretta Java 8 testing3 days4/6/2305/30/23CompleteLEXEVS-5331CTS2 Corretta Java 8 testing1 day4/6/2305/30/23CompleteLEXEVSCTS2-433lexevs remaining dependency updates - design10 days4/10/2304/21/23CompleteLEXEVS-5333lexevs remaining dependency updates - implementation20 days04/13/2304/24/23CompleteLEXEVS-5334lexevs remaining dependency updates - unit testing2 daysIn ProgressLEXEVS-5335CTS2 remaining dependency updates - design1 day04/19/23CompleteLEXEVSCTS2-435CTS2 remaining dependency updates - implementation3 daysCompleteLEXEVSCTS2-436CTS2 Unit testing2 daysCompleteLEXEVSCTS2-437QA2 daysComplete

LEXEVSCTS2-438

LEXEVS-5336

Deployment5 days (elapsed)Completelexevs-service-rest-docs vulnerability update design2 days05/15/2305/27/23CompleteLEXEVSCTS2-440lexevs-service-rest-docs vulnerability implementation4 days05/15/2305/27/23CompleteLEXEVSCTS2-441lexevs-service-rest-docs unit testing1 day05/27/23In ProgressLEXEVSCTS2-442lexevs-service-rest-docs QA

1 day

LEXEVSCTS2-443lexevs-service-rest-docs deployment4 days (elapsed)lexevs-service-rest-docs Java 8 testing

2 days

05/27/2305/30/23















Total Effort (Approximately)104 days




...