NIH | National Cancer Institute | NCI Wiki  

WIKI MAINTENANCE NOTICE

Please be advised that NCI Wiki will be undergoing maintenance on Thursday, May 23rd between 1200 ET and 1300 ET.
Wiki will remain available, but users may experience screen refreshes or HTTP 502 errors during the maintenance period. If you encounter these errors, wait 1-2 minutes, then refresh your page.

If you have any questions or concerns, please contact the CBIIT Atlassian Management Team.

Error rendering macro 'rw-search'

null

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Ticket Description Actions, Update
Request from LRbanner referencing EVS Explorer

If NCI Terms Browser down, banner should point people to EVS Explorer.

Will put in a request for STAGE after Swathi does testing

NCI-RITM046506 MEME URI not working, hostname usable as workaround
NCI-RITM0509062 Install Tomcat 9 on Dev

SYSTEMS
EVS transition to virtual machines

STATUS:We need to have a decision about how to handle PROD VM server not being ready at the moment.

We were going to wait to switch STAGE from on prem to VM once PROD server is ready; so we can switch both PROD and STAGE at same time . 

So how do we handle the OS conversion then? Do we push for PROD VM to be made? Wait to build the VM after we convert STAGE and then PROD to Oracle Linux 7?

  • DECIDED: conversion first, then transition to VMs
  • we are probably a ways from PROD VM; STAGE VM saw issues pop up during transition



LEXEVS UPDATES

Monthly Planning and Focus

Completed Sprint - Sprint 216 (Jan 9 - Feb 2) -

Current Sprint  - Sprint 217 (Feb 2 - Mar 2) - Sprint 217

For the month of February 2024

Technical Debt remediation

LexEVS Code Debt Refactoring - Java 17 refactoring currently is in progress

OS Updates

QA conversions starting

Report Exporter
  • Working on templating - on pause for the moment
  • Wait time indicator work is being tested, being moved to QA


Security


Statistics Dashboard

OBJECTIVE 
Complete Migration of Statistics Dashboard from SumoLogic to DataDog by March 2024.

STATUS

  • S3 bucket has been created, but is blocked by next step of installing a Datadog / AWS integration. 
  • RUM installation started

ACTIONS

  •  Benson, Mark (NIH/NCI) [C] to create S3 bucket - under 'EVSTOOLS'
    •  will need additional work to install Datadog / AWS integration. working with Cyrus and Systems.
Comparison/Mapping Tool

On Hold

AWS Cloud to be in Separate Account

Waiting on AWS team

Team Absences


Mayo Team - 

MSC - 

Leidos - 

QA - 

Gov - 



EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

EVS PROD Outage

Scott made the point about needing metrics for server performance, resources when issues/outages occur.


DATA UPDATES
Data


BROWSER UPDATES

Browser
  • A proposal for handling the Contact Us SPAM is being drafted.
  • Requesting top, vmstat, diskf logs during reboot of Prod

QA UPDATES

QA




TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Mark Benson TPM Update

...