SYSTEMS
Systems

Discussion Points: No discussion points this week. 

Decision Points: 


LEXEVS UPDATES

LexEVS Sprint Status


Current Sprint - Sprint 183 (March 24, 2021 – April 3, 2022)

16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint183
  • Activities
    • Updates to Spring for LexEVS - working through the DAO and registry work
    • Noted Vulnerability now known to earlier Spring Version
LexEVS Spring Updates

Discussion Points:

  • Meeting to be scheduled with Denise?
    • No longer dependencies on caDSR app
    • There is a link from caDSR browser to old browser
  • Awareness of vulnerability
  • Completed several dao layers
  • Need to add Metathesaurus RRF, other formats for loading to scope
  • Still on schedule
  • OCPL relies on CTS2 - still trying to understand how they are using it
    • Reply arrived this morning
  • .Multiple teams - trying to identify which groups are using it and how

Decision Points:  

  • Agreed that CTS2 is the priority as remote is not used.
  • Jason mentioned Kim uses the remoteAPI to do development. Need to document changes that he will need to know
    • Kim asked for a link to the code branch we are working upon
  • Scott mentioned we would need to reload all of the data

CBIIT's enterprise github

Discussion Points:

  • Complete

Decision Points:

BOD 22-01 HHS Vulnerability Disclosure Link

Discussion Points:

  • Complete

Decision Points:

Meta Tree investigation

Discussion Points:

  • Nothing new to report

Decision Points:

CTS2 Mapping/URI Resolver

Discussion Points:

  • On Hold

Decision Points:

Statistics Dashboard

Discussion Points: 

  • Met with Manish and others
  • logs cannot be restored for the missing weeks of April and Months before that. 
  • We should now have at least 90 days of logs.  
  • Scheduled view was supposed to be the replacement.
  • Still no set of implementation instructions.

Decision Points:

2-prong effort:

  • Mark to communicate with group to explain our dependencies and the situation we have been placed in. Request a written response and the ID of the Federal person overseeing this.
  • Scott Put together a plan or description of the efforts we will go through to mitigate the issues going forward.
Comparison/Mapping Tool

Discussion Points

  • On Hold

Decision Points:

EVS transition to virtual machines

Discussion Points:

Decision Points:

Team Absences

Mayo Team

  • Scott - 
  • Tracy - Thursday AM this week


Vulnerability testing



EVS SERVICE AND ARCHITECTURE GROUP UPDATES

EVS Service and Architecture Group

Discussion Points:

Decision Points:


DATA UPDATES
Data

Discussion Points: New NCIt started May 31 (yesterday)

Decision Points:


BROWSER UPDATES

Browser

Discussion Points: No releases going through tiers currently

Decision Points: 


QA UPDATES

QA

Discussion Points: 

  • Finished EVSRestAPI and Explorer 1.6, being deployed to Stage
  • Data deployment to Stardog today 22.05e

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 

...