Goals
Goal | Assigned to | Accomplished? | |
---|---|---|---|
1 |
Lay out architecture. | Amit | Yes - wiki pages updated with CI/CD Architecture, DevOps Plan, System Architecture | |
2 | Lay out key components. | Ye | Yes - components were laid out in JIRA tickets - many details need to be defined in next Sprint |
3 | First draft of wireframes for front-end. | Dimitri | Yes - some gaps remain, however, main pages were outlined. |
Begin design for MVP
Retrospective Results
Author | Category | Card Title | Comments | |||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Matthew BKevin | What Didn't Work | Project X really took a bite out of our productivity for this sprint. | Amit M, Apr 23 2019 - Indeed! | Matthew B | Suggestions for Improvement | Define teams and team leaders for MVP - Front-end, back-end, Data munging, QA? | Philip M | What Worked | We finally opened the lid on user interactions and expectations via Greg Tawa | Amit M, Apr 23 2019 - Got useful information regarding the submission process.Philip M | What Didn't Work | Complications around the NCATS data prevented us from making anywhere near as much progress on getting the data into ICDC as planned for the sprint |
Matthew B | Suggestions for Improvement | Dimitri wants access to source files in future. | Matthew B, Apr 23 2019 - raw data access to look at file formats. | Matthew B | Suggestions for Improvement | Can we pare back on some of the meetings? - Dimitri | Matthew B, Apr 23 2019 - Perhaps one weekly team meeting with everyone and no standups?
Tickets
Worked | Transformations worked as Philip expected. Loading into Gen3 worked as expected. | ||
Dimitri | What Worked | Requiring a group Project Scope helped map out steps going forward. | |
Ann | What Worked | The trainings have helped to provide me with an idea of what the project is about. |
Tickets
Jira | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|