Ticket Description Actions, Update

NCI-INC0748380
NCI-RITM0430005

Testing Corretta Java 8 on Dev

RITM0446147

  Install Corretta OpenJDK on QA2
waitingTomcat set up and smoke tested on Dev. Ready to proceed to QA 

SYSTEMS
EVS transition to virtual machines

Status:

  • Aaron Taye is the project manager and will be coordinating team; waiting for progress report. We're reached out again and we're still waiting. Will escalate to next level asking for status.
  • Work progressing per wiki page
  • Need for followup?

Reference: Wiki page: Server Migration 2021

Systems

See ticket chart (above)


LEXEVS UPDATES
Future Planning
    Priorities and Goals for May are
  • Test Java 8 migration to Corretto
  • Start
  • Complete Report Exporter refactoring and dependency

  • updateWrap up
  • updates

    • (see EVSREPEXP-475 -> 483)

  • Complete all other dependency updates

  • Work
  • Prepare for RC2 release

  • Get sign-off on RMI

  • retirement plan
  • Write and review Comparison Mapping Tool User Stories and Requirements
  • Priorities and goals for June being reviewed
  • Retirement plan

  • Create a Work Breakdown Structure (WBS) for SumoLogic to DataDog Transition

  • Create Report Exporter Roadmap and Gap analysis of functionality and features such as

  • Groom backlog and prioritize existing bugs

LexEVS Sprint Status


Starting next cycle will go to month-long sprints
Technical Debt remediation

LexEVS Code Debt Refactoring

Java 8 CorrettaCorretta Java 8 installed on Dev
  • loader testing successful
  • Tomcat services smoke test successful

    Report Exporter
      • Discussion Points:

        • Working on update to Vue3 (JavaScript Framework). EVSREPEXP-451
          • master ticket: EVSREPEXP-442 - Migrate Vue.js version from 2.0 to 3.0
          • Description
            • On QA and being tested
              • Jira tickets created for each feature, as requested
              • QA team reported
    8
              • 9 issues
    2
              • 4 moved to QA
    3
              • 1 on Dev
    3
              • 4 being worked on locally
    Duplicate issue being worked on
    • Completed and merged into branch
        • Vulnerable dependencies - next on deck

    Decision Points:

    caDSR Query

    Discussion Points:

    • Value Set issue discovered : downloading csv does not return all concepts - on Stage, but have another fix on QA with request to go to Stage.
      • On Prod.  Vulnerabilities were false positive
      - on Prod
      • On Prod.  Vulnerabilities were false positive

    Statistics Dashboard

    Discussion Points: 

    • Statistics

    Statistics Dashboard

    Discussion Points: 

    • Google analytics - Retiring GA and going to GA4
        • EVSExplore
          • Possible URL change (semantics.gov)
            • On Prod
          • GA4 pending the URL fix
        • NCI Terms Browser - On Prod
    • Statistics - Sumo Logic
      • Sumo logic will be discontinued
      • There will be an active migration effort to Datadog

    Decision Points:

    Comparison/Mapping Tool
    • User stories, work on hold for now
    AWS Cloud to be in Separate Account

    Discussion Points

    • Frozen

    Decision Points:

    Team Absences


    Mayo Team - Scott out 6/2 - 6/6? , Andrew out 6/26 to 7/5

    MSC -

    Leidos -

    QA - Swathi ~ 6/6 .  Reza Mehri and Anika to backup

    Gov - Lyubov out 5/30 to 6/6 


    EVS SERVICE AND ARCHITECTURE GROUP UPDATES
    EVS Service and Architecture Group

    Discussion Points:

    • Access to limited Metathesaurus for testing - supplied by B.Carlsen years ago
      • Access to Metathesaurus generation tool
      • Need location to place the toolS3 bucket set up and tested
    • What is minimum set of vocabs needed for testing browsers
      • Per Kim - if NCIt works other will work.
      • Meta needed for NCIm
      • GO for mappingsNCIt, NCIm, GO

    Decision Points:


    DATA UPDATES
    Data

    Discussion Points: 

    • New NCIt 23.05e - in processing

    Decision Points:

    BROWSER UPDATES

    • - on Data-QA, ready for review but editors out of office today
    • Monthlies next week

    Decision Points:


    BROWSER UPDATES

    BrowserBrowser
  • caDSR new tool CDE browser links to terms browser.  URLs have been updated correctly and promoted in concert with CDE Browser
    • on Prod
  • Scan found stage tier issue with vulnerability.  False positive
    • Make sure metabrowser extension is incorporated - RC2 released and given to Kim
    • Metadata for VKC links to be removed - ticket created
    • Some issues with indexes on new Stage - needs followup

    QA UPDATES

    QA

    Discussion Points: 

    • Completed regression 23.05e on EVSRestAPI Prod
    • 2 more tickets for Report Exporter RC3 being tested
    • 1.8 tag for RestAPI and Explorer being tested
    • Progression 2.19 Term Browser on Stage and Production
    • Working on 2.305 REST APIs - on Stage
    • Report Exporter RC2 - 2 tickets to be tested
    • Corretta - waiting on QA deployment. Will work with Mark to schedule

    Decision Points: 



    TERMINOLOGIES LIFECYCLE REPORT

    Terminology Updates and Schedule 

    Discussion Points: 

    Decision Points: 

    Mark Benson TPM UpdateInformation Security training should be completed as soon as possible, please

    Data deployment proposal


    LexEVS Technical Debt Progress

    ...