NIH | National Cancer Institute | NCI Wiki  

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Ticket Description Actions, Update

NCI-RITM0512149

Security consult about IP traffic to Prod
Asked for dynamic IP throttling
Working to escalate using WAF (Web Application Firewall)
Mark to keep close eye on this
  •  Temporarily block Singapore traffic
NCI-RITM0528879Install Tomcat9 deployment track for ncitermform to evs-jenkins
Elevated on 5/29



EVS transition to virtual machines

STATUS:

  • Prod2 server up and running - completed tested
  • DATAQA started


  • Tomcat 8.5 reached EoL - needing new stacks for all tiers
    • Oracles OES8, Tomcat 10, Java 17 
      • Java 17 implemented
      • Others to follow once 17 on Pro
    • Options
      • Tomcat 9 and Java 17 installed on Dev
      • evs-jenkins working for NCItBrowser and lexevscts2
      • OES8 could come later
    • NCItermform installed on Dev - needs testing
  • Tomcat 9 installed on Dev.  
    • Recoding needed for NCIm
      • Similar to work done on browser
    • NCI Term Form Jenkins requested
    • NCIm track created
  • Should get started on QA for browser
    • No deployment track noted yet
    • Terms browser ready to move





LEXEVS UPDATES

Monthly Planning and Focus

Completed Sprint - Sprint 219 (Mar 5 - May 10) -

Current Sprint  - Sprint 220 (May 13 - May 31) - 

For the month of May 2024

Report Exporter
  • Working on templating starting
    • Doing phase 1 - moved to Stage
      • Stage EVS Rest API having issues
      • Cloud team addressing the issue
    • In progress: implement file-based template storage
      • Code completedOn Dev issue with Rest APi affecting testing - working currently
      • Tomcat 9 testing - resolved on Dev
        • Systems working on QA
    • Moving Dev and QA to run from 7AM-10PM


Security

Tomcat 8.5 is EOL - risk if new vulnerability discovered

  • Oracle Java 8 - still being used on DataQA
    • Still present on other servers, in $PATH
    • Java 17 being added next week
    • Current proposal is to not push to DataQA, let it retire
  • Need to check on Processing Server
  • FTP1 has .bash_history file
    • Concerns about directory listing

Statistics Dashboard

OBJECTIVE 
Complete Migration of Statistics Dashboard from SumoLogic to DataDog by June 1 2024.  

STATUS

S3 bucket has been created
  • Working on integration
  • successfully tested refresh

    • need to operationalize - testing going on
    • New Dashboards being made - can be shared
    • All May logs loaded from Sumo - being tested
        Link: Sharepoint Project Task Checklist
          • Testing rehydration of converted Sumo Logic logs
      Comparison/Mapping Tool

      On Hold

    • Moved to 7-10
    • shutdown to save resources?Is old architecture so needs update work if kept
    • Per Lyubov - can shut down server for now
      •  Tracy to request shut down of instance to save resources
      AWS Cloud to be in Separate Account

      Waiting on AWS team

      Team Absences


      Mayo Team - Andrew June 17-23,  Scott off July 1-8

      MSC -  Jason, June 17th → 21st

      Leidos - 

      QA - 

      Gov - 



      EVS SERVICE AND ARCHITECTURE GROUP UPDATES
      EVS Service and Architecture Group

      Discussion about Java 17 migration and remediation

      There is an issue in Term Browser where several of the mappings show a null for the release. There is a choice: do a separate release to fix this or if we want to make it as part of the Java 17 release.

      DECIDED: Keep it as part of the Java 17 release (even if it means waiting longer)

      LexEVS Retirement

      We have a meeting scheduled for Fri 10am, checklist, gap analysis 


      DATA UPDATES
      Data 

      Reviewing next data release, 24.05d, which is ready reviewing at the data QA now. Next week will do Monthly vocabularies.


      BROWSER UPDATES

      Browser
      •  

      QA UPDATES

      QA 

      completed a regression execution for the May 2024 data deployment release on EVS APIs (completed on production environment).

      There is a release candidate for EVS report exporter, Andrew is working on a set of issues (e.g. dependency).


      TERMINOLOGIES LIFECYCLE REPORT

      Terminology Updates and Schedule 

      Mark Benson TPM Update

      Funding for LexEVS dramatically reduced in CY25.  Preparing for sunsetting of components

      Working on checklists for what should be done

      • Gap analysis for EVS Explore
      • Longtime needs examination
      • Handoff documentation for operations applications
      Please complete information security refresher ASAP.  Call for people to complete their required trainings.


      Vocabularies Slated for Production

      ...