Page History
...
LexEVS Spring Migration Progress
Anchor | ||||
---|---|---|---|---|
|
Spring Related Update | Estimated Effort | Status |
---|---|---|
Spring Related Update | Estimated Effort | Status |
Ivy Dependency Update | 3 days | Complete |
Ibatis to Mybatis xml conversion | 3 days | Complete |
Compile capable code conversion | 3 days | Complete |
Application context startup | 1 week | Complete |
CodingSchemeDao Verification tests / Code Corrections | 10 days | Complete |
Association Dao Verification tests / Code Corrections | 10 days | Complete |
Registry Dao Verification / Code Corrections | 10 days | Complete |
Coded Node Graph Dao / Code Corrections | 10 days | Complete |
Entity Dao / Code Corrections | 10 days | Complete |
NCI History Dao / Code Corrections | 3 days | Complete |
Property Dao / Code Corrections | 10 days | Complete |
Revision Dao / Code Corrections | 2 days | In Progress |
System Release Dao / Code Corrections | 1 day | Complete |
Pick List Dao / Code Corrections | 1 week | Not Started |
Pick List Entry Dao / Code Corrections | 1 week | Not Started |
Source Asserted Value Set Dao / Code Corrections | 2 days | Complete |
Value Set Definitions Dao / Code Corrections | 10 days | Complete |
Value set Hierarchy Dao / Code Corrections | 1 day | Complete |
Vaue set Definition Entry Dao / Code Corrections | 2 days | Complete |
Value Set Entry State Dao / Code Corrections | 2 days | Complete |
Value Set Property Dao / Code Corrections | 1 week | Complete |
Versions Dao / Code Corrections | 2 days | In Progress |
Testing/ Verification | 1 week | Not Started |
Load tests | 2 weeks | In Progress |
Testing verification Recoding | 10 days | In Progress |
Full system test | 1 day | Not Started |
LexEVS Remote | 3-4 weeks | Not Started |
LexEVS CTS2 Service | 2-3 weeks | In progress |
Total Effort (Approximately) | 4-5 months |
...
Vocabulary Name | Local Name | Version | Arrival Date | Loaded to data-qa DB | Date to Stage | Date to Production | ||
---|---|---|---|---|---|---|---|---|
Vocabulary Name in LexBIG | Short Name | Version identifier | Date the vocabulary arrived for processing | Has the vocabulary been loaded to the data-qa database? | Approximate date the vocabulary version is scheduled to move to staging | Approximate date the vocabulary version is scheduled to move to production | ||
NCI Thesaurus | NCIt | 22.06d | 06/29/2022 | yes | 07/ | 0507/22 | 07/ | 0608/22 |
NCIt-HGNC | NCIt-HGNC | n/a | ||||||
SwissProt | SwissProt | n/a | ||||||
ChEBI | ChEBI | v211 | 07/06/2022 | yes | 07/11/22 | 07/12/22 | ||
GO | GO | Jul2022 | 07/06/2022 | yes | 07/11/22 | 07/12/22 | ||
HGNC | HGNC | Jul2022 | 07/06/2022 | yes | 07/11/22 | 07/12/22 | ||
MED-RT | MED-RT | 07/05/2022 | yes | 07/06/22 | 07/06/22 |
QA Schedule and Status
...