Spring Related Update | Estimated Effort | Status |
---|---|---|
Spring Related Update | Estimated Effort | Status |
Ivy Dependency Update | 3 days | Complete |
Ibatis to Mybatis xml conversion | 3 days | Complete |
Compile capable code conversion | 3 days | Complete |
Application context startup | 1 week | Complete |
CodingSchemeDao Verification tests / Code Corrections | 10 days | Complete |
Association Dao Verification tests / Code Corrections | 10 days | Complete |
Registry Dao Verification / Code Corrections | 10 days | Complete |
Coded Node Graph Dao / Code Corrections | 10 days | Complete |
Entity Dao / Code Corrections | 10 days | Complete |
NCI History Dao / Code Corrections | 3 days | Complete |
Property Dao / Code Corrections | 10 days | Complete |
Revision Dao / Code Corrections | 2 days | In Progress |
System Release Dao / Code Corrections | 1 day | In ProgressComplete |
Pick List Dao / Code Corrections | 1 week | Not Started |
Pick List Entry Dao / Code Corrections | 1 week | Not Started |
Source Asserted Value Set Dao / Code Corrections | 2 days | Complete |
Value Set Definitions Dao / Code Corrections | 10 days | Complete |
Value set Hierarchy Dao / Code Corrections | 1 day | Complete |
Vaue set Definition Entry Dao / Code Corrections | 2 days | Complete |
Value Set Entry State Dao / Code Corrections | 2 days | Complete |
Value Set Property Dao / Code Corrections | 1 week | Complete |
Versions Dao / Code Corrections | 2 days | In Progress |
Testing/ Verification | 1 week | Not Started |
Load tests | 2 weeks | In Progress |
Testing verification Recoding | 10 days | In Progress |
Full system test | 1 day | Not Started |
LexEVS Remote | 3-4 weeks | Not Started |
LexEVS CTS2 Service | 2-3 weeks | Not Started |
Total Effort (Approximately) | 4-5 months |
...
SECTION FOR FUNCTIONAL SYSTEM TESTING STATUS ::
Application and Version | Percentage Complete | Estimated Completion Date per Iteration | Priority Level | Type Of Testing | Current Tier for Release (DEV, QA, Stage, Prod) | Expected Production Date |
EVS REST API (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS Explore (v1.6) | 100% | 5/27/2022 | High | Progression + Regression | QA | 6/6/2022 |
EVS REST API(v1.6) | 100% | 6/1/2022 | High | Regression | Stage | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/2/2022 | High | Regression | Stage | 6/7/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/1/2022 | High | Regression | Stage | 6/3/2022 |
EVS REST API(22.05e) - Monthly Data Deployment | 100% | 6/3/2022 | High | Regression | Production | 6/3/2022 |
EVS REST API(v1.6) | 100% | 6/6/2022 | High | Regression | Production | 6/6/2022 |
EVS Explore(v1.6) | 100% | 6/7/2022 | High | Regression | Production | 6/7/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/3/2022 | High | Regression | Stage | 6/6/2022 |
NCIt,NCIm,TermForm(22.05e + GO & HGNC Jun 2022 Deployment) | 100% | 6/6/2022 | High | Regression | Production | 6/ |
8/2022 |