Report


Goals


Goal

Assigned To

Accomplished?

1

...

Streamline C3D export and ETL process

Phil/LilyYes
2

Test data upload repeatedly (ETL)

Ye/Phil/AmitYes
3

Conduct Demonstration (one internally and one for client)

Matt/AmitWill be done except client
4

Provide specific vocabulary for data model (BRIDG)

MarkPartial
5

Define specific constraints to graph data model (e.g., required vs. optional)

PhilPartial
6

Conduct test of native graph vs. post-gres/graph

MarkPartial
7

Define team GitHub process and educate the team.

AmitPartial


Retrospective Results

AuthorCategoryCard Title
Matthew BWhat WorkedScrum appears to be more efficient.
Matthew BWhat WorkedGood to have Erika there in Scrum
Matthew BWhat WorkedTeam Chemistry is really good.  Never boring.
Matthew BWhat WorkedDemo provided a solid goal for performance.
Matthew BSuggestions for ImprovementIf QA is not necessary, go right to close.
Matthew BSuggestions for Improvementtransfer tickets when done with your part to next person for QA (if needed).
Matthew BSuggestions for ImprovementCould try doing sprint loading based on velocity.
Matthew BSuggestions for ImprovementPeople should try to record ticket updates (including closure) as soon as possible to best affect burndown rate.


Tickets

Sprint 3

Jira
serverNCI Tracker
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQuerySprint=1750
serverId7954a81f-12da-3366-a0ef-97c806660e7c