NIH | National Cancer Institute | NCI Wiki  

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migrated to Confluence 5.3

 Attendees

NameRolePresent
Wright, Larry NIH/NCI  x
Fragoso, Gilberto NIH/NCI    x

De Coronado, Sherri    

NIH/NCI   x

Safran, Tracy

NIH/NCI   x
Ong, Kim L
ISx
Lucas, Jason R
ISx
Bauer, Scott  Mayox
Stancl, Craig
Mayox
Endle,  CoryMayox
Wynne, Robert    NIH/NCIx
Pan, JJ
NIH/NCI [E]x
Tran, Tin    NIH/NCI [C] x
Ahmed, Shamim
NIH/NC [C]  
Haber, Margaret (NIH/NCI) 
Roth, Laura (NIH/NLM)  
Ramani, Vivek (NIH/NCI) [C]  
Carlsen, Brian (NIH/NCI) [C] 
Wong, Joanne   

Kuntipuram, Kumar

 x

 

Action Items

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
64ScottTo follow up on URI's on OWL2 with Harold.   on hold
136ScottPoint the CTS2 API page to PROD (wiki) - originally planned on Stage, but now planning on PROD.   done
154Larry

Provide an email update to NCBO, NLM, and Mayo with current activities and what has been built.

   

open

155KumarVerify that funds can be extended through Oct.2014.04.30  open
156Scott

Scott to work with Gilberto to determine what is needed for OWL 2 requirements

2014.04.30  

open

157Craig

Include the value set and namespace tacks back into plan (in case we do have time or extension)

2014.04.30  open
158Jason

Jason to send note to Michael and Jacob (include Scott) to understand what the work around is for Struts

2014.04.30  open
159Tracy/ScottTracy/Scott to provide example  for UMLS problem and send that on to Alameda team.2014.04.30  open
160ScottScott to submit feature request to expand value set definitions (requires a model change).2014.04.30  

open

161CoryAdd service information to include links (rest calls).2014.04.30  open
162Cory/Craig

Talk with Kevin about NCBO and what is exposed via value set client. 

2014.04.30  open
163Craig

Jason has dependencies so Craig to work with Jason on plans and will update and send out to the group.

2014.04.30  open
164CoryCory to add implementation to CTS2 implementations page.2014.04.30  open

Progress

Immediate Priorities and Problems (Mayo Team)

Scott:  CTS2 1.1 Based Framework, discussions, widget update

  • Completed informatics deployment of LexEVS CTS2 service.
  • Discussions with Rob, Tracy and Kim.
  • Widgets updated to point to new content.  

Cory:  CTS2 Client UI, Informatics Deployment

  • Value Set Viewer deployment on informatics.
  • About page updated.  will look at during demo.
  • NLM testing - authentication to be resolved ASAP.
  • Need to test on IE and Firefox (latest).  

Craig: Project Plan Updates

  • Kumar to verify that funds can be extended through Oct.
  • OWL 2 features - Apelon and NDFRT needs to user OWL 2 features that we currently do not have.  This may need to be included earlier than the end of the release.  Scott to work with Gilberto to determine what is needed.  
  • Include the value set and namespace tacks back into plan (in case we do have time or extension)
  • Jason has dependencies so Craig to work with Jason on plans and will update and send out to the group.
 

 

 

Returning coding schemes and versions from value set definitions
  • Reported by Kim (in JIRA)
  • Consider documenting the better performing code (remote).
  • No longer a high priority.
  
Struts update 2.3.16.2
  • Scott - Need to understand how the work-around works and what can be done.  (configuration update via systems team)
  • Once complete work around, then testing needs to be done. 
  • Since there is no code running against Struts, then a simple test can be done.
  • If a war file needs to be generated, then follow the same process that was just completed for the 6.1.1 release.
  • Barry and Preston will need to decide what they want to approve. 
  • Gilberto to talk with Preston.   Gilberto has already checked with Bruce and it sounds like the work-around will suffice.  
  • Jason to send note to Michael and Jacob (include Scott) to understand what the work around is.  
  • May want to consider this work-around fix for LexEVS 6.0 as well.   Additionally we could consider dropping 6.0 if 6.1 is fully backwards compatible. 
  
caDSR and Value Set and other URIs (Weekly Status)

No updates.

  
Max clause count issue (update)No problems so far after max was updated.  

  

  
UMLS Mapping Files

Scott did get files downloaded for testing.   In MRSAT file, we look for CUI, but the CUIs do not seem to exist - resulting in no metadata. 

Scott to look closer at this with the current file set. 

Tracy/Scott to provide example and send that on to Alameda team.

  
ARC Meeting

ARC document created and sent to Jason, Larry, Sherri and Gilberto.

Jason submitted DRT ticket to get meeting scheduled. 

  
VS created using Meta (Rob)Scott suggests that we submit feature request that will expands value set definitions (requires a model change).  
UI Demo (Cory)

Consider adding service information to include links (rest calls).

Cory and Craig to talk with Kevin about NCBO and what is exposed via value set client.  

Cory to add implementation to CTS2 implementations page.

  

 

 

 

JIRA Issues

Description
Jira
serverNCI Tracker
keyLEXEVS-570
Jira
serverNCI Tracker
keyLEXEVS-573
Jira
serverNCI Tracker
keyLEXEVS-579
Jira
serverNCI Tracker
keyLEXEVS-586
Jira
serverNCI Tracker
keyLEXEVS-594
Jira
serverNCI Tracker
keyLEXEVS-597
Jira
serverNCI Tracker
keyLEXEVS-598
Jira
serverNCI Tracker
keyLEXEVS-599
Jira
serverNCI Tracker
keyLEXEVS-605
Jira
serverNCI Tracker
keyLEXEVS-606
Jira
serverNCI Tracker
keyLEXEVS-607
Jira
serverNCI Tracker
keyLEXEVS-608
Jira
serverNCI Tracker
keyLEXEVS-609
Jira
serverNCI Tracker
keyLEXEVS-612
Jira
serverNCI Tracker
keyLEXEVS-613
Jira
serverNCI Tracker
keyLEXEVS-615
Jira
serverNCI Tracker
keyLEXEVS-616
Jira
serverNCI Tracker
keyLEXEVS-617
Jira
serverNCI Tracker
keyLEXEVS-618
Jira
serverNCI Tracker
keyLEXEVS-619
Jira
serverNCI Tracker
keyLEXEVS-620
Jira
serverNCI Tracker
keyLEXEVS-621
Jira
serverNCI Tracker
keyLEXEVS-622
Jira
serverNCI Tracker
keyLEXEVS-623
Jira
serverNCI Tracker
keyLEXEVSCTS2-2
Jira
serverNCI Tracker
keyLEXEVSCTS2-3

Project Plan Changes

#DescriptionDue DateResourcesNotesRisksMitigation
 None     
       
       

 Planned Activities

Area of InterestDetails
VSMC definitionNeed a dialog defining module use around ResolvedValueSets
Update LexEVS CTS2 Service to CTS2 1.1Need deployment tests
Work on a variety of EVS JIRA PrioritiesScripting, convenience methods, tree extension namespace issues

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
         
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
      
      
      

Dependencies

Opened DateDescriptionAssigned