Deliverable Artifacts
Deliverable | 4/10 | 5/10 | 6/10 | 7/10 | 8/10 | 9/10 | 10/10 | 11/10 | 12/10 | 1/11 | 2/11 | 3/11 |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Management Plan | Revised |
|
|
|
|
|
|
|
|
| Final | |
Software Code Base | Draft | Draft | Draft | Draft | Draft | Draft | Draft | Draft | Draft | Draft | RC | Final |
Monthly Status Report | Report | Report | Report | Report | Report | Report | Report | Report | Report | Report | Report | Report |
Draft Design Review Package |
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final | |
Test Package |
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final |
Test Plan |
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final |
Test Report |
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final |
ECCF Documentation |
|
|
| Draft | Revised | Revised | Revised | Revised | Revised | Revised | Revised | Final |
caBIG Compatibility Package |
|
|
| Draft |
|
|
| Revised |
|
| Final | |
Deployment Package |
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final |
Installation Package |
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final |
Release Notes |
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final |
Installation Guide |
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final |
Software Product Documentation |
|
|
|
|
|
|
| Draft | Revised | Revised | Revised | Final |
BDA Compliance Package |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
BDA Compliance Matrix |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
BDA Feedback Report |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
Product Install QA Report |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
BDA Software Test Plan and Scenarios |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
BDA Software Test Results |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
BDA Software Code |
|
|
|
|
|
|
| Draft |
|
| Revised | Final |
Section 508 Compliance Package |
|
|
|
|
|
|
|
|
|
| Draft | Final |
Team
Role | Member |
---|---|
Project Director | Joshua Phillips |
Project Manager | Beate Mahious |
Subject Matter Expert | Ram Chilukuri |
Architect | Tom Digre |
Lead Business Analyst | TBN |
Senior Business Analyst | Patrick McConnell |
Senior Software Engineer | TBN |
Software Engineer | TBN |
Quality Assurance Engineer | TBN |
Technical Writer | TBN |
...