# | Assigned | Description | Date Identified | Due Date | Date Completed | Comments | Status |
---|---|---|---|---|---|---|---|
1 | Reza | Start exploring ways to automate Protégé 5 testing | 11/30/2015 | 4/29/2016 | 12/1/2015: Held a meeting with dev team and QA to discuss approach. Will continue trying out tests. 2/8/2016: QA testing tools for automatiionfor automation 5/6/2016: Using HP-UFT for automation | ClosedIn Progress | |
2 | Bob | Provide detailed project plan with milestone dates after getting his subs input | 1/4/2016 | 5/6/2016 | 3/1/2016: Received initial plan without milestones dates. Have requested the project plan be updated with more details to enable proper project planning. 5/6/2016: Was provided updated plan. The plan is a living document and will continue to be updated on a regular basis | ClosedIn Progress |
Progress
Area of Interest | Details | ||
---|---|---|---|
Wiki | Updated Project Status Wiki | ||
Protégé 5 | Started initial Continuing development work | ||
QA | Continuing testing Protégé 5 completed modules. | Resource | Vendors new resource started work on the project. |
JIRA Issues
Issue Number | Description | Status |
---|---|---|
...
Area of Interest | Details |
---|---|
QA | Work with Dev to automate Protégé 5.0 testing. Also figure out Continuous integration |
Dev | Continue Protégé 5.0 development |
...