Panel | ||||
---|---|---|---|---|
| ||||
|
Panel | ||
---|---|---|
| ||
Current Agile Board
Sprint 213
- Dates: Oct 03, 2023 -
- Goal
- Sprint Report
- Retrospective
- Artifacts
Sprint 212
- Dates: Sep 03, 2023 - Sep 29, 2023
- Goal
- Continue Report Exporter digital styling
- Continue ehcache work
- Testing of LexEVS/CTS2 Spring update
- Sprint Report
- Retrospective
- Artifacts
Sprint 211
- Dates: Jul 31, 2023 - Sep 03, 2023
- Goal
- Digital styling in Report Exporter
- Digital styling in CTS2 docs
- Update Spring to 5.3.29 - critical vulnerability
- Sprint Report
- Retrospective
- Artifacts
- CTS2 Service 2.2.1
Sprint 210
- Dates: Jul 03, 2023 - Jul 31, 2023
- Goal
- MyBatis configuration issue for Mass Mappings
- LexEVS/CTS2 dependency deployment
- Browser deployment work for Spring 5
- Sprint Report
- Retrospective
- Artifacts
- CtS2 Service 2.1.1
Sprint 209
- Dates: Jun 06, 2023 - Jul 03, 2023
- Goal
- LexEVS Unit testing
- Continue ehcache work on LexEVS
- Remediate QA issues in Report Exporter
- CTS2 miscellaneous tickets
- Sprint Report
- Retrospective
- Artifacts
- New Report Exporter 2.0.0 release candidate
Sprint 208
- Dates: May 23, 2023 - Jun 06, 2023
- Goal
- Castor work completed
- ehcache work begun
- Corretto testing complete, moved to QA
- Sprint Report
- Retrospective
- Artifacts
Sprint 207
- Dates: May 09, 2023 - May 23, 2023
- Goal
- Work begun on removing castor
- Corretto Java testing continues
- lexevs-service-rest-docs continues
- Sprint Report
- Retrospective
- Artifacts
- Report Exporter Spring 5 - v2.0.0
Sprint 206
- Dates: Apr 27, 2023 - May 09, 2023
- Goal
- NCIt Browser deployed to Dev
- Work started on lexevs-service-rest-docs vulnerability update
- CTS2 vulnerable dependency completed
- Agile Board
- Sprint Report
- Retrospective
- TBD
- Artifacts
- CTS2 vulnerable dependency work released to QA - v2.2.0
Sprint 205
- Dates: Apr 10, 2023 - Apr 27, 2023
- Goal
- Vue 3 moved towards release
- LexEVS release candidate on Dev
- CTS2 work begun, incorporating updated LexEVS
- Testing of Corretto Java VM begun on Dev
- Agile Board
- Sprint Report
- Retrospective
- TBD
- Artifacts
- Report Exporter Vue 3 released to QA
- LexEVS vulnerable dependency work released to QA - v6.6.1
Sprint 204
- Dates: Mar 28, 2023 - Apr 10, 2023
- Goal
- Update MyBatis configurations for Mappings in Spring 5
- Update vulnerable dependencies in lexevs
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Agile Board
- Sprint Report
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 203
- Dates: Jan 30, 2023 - Mar 28, 2023
- Goal
- Update vulnerable dependencies in lexevs
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Metathesaurus CUI obsolete fix
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 202
- Dates: Dec 23, 2022 - Jan 30, 2023 (4 weeks)
- Goal
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Vulnerable dependency update
- Metathesaurus CUI obsolete fix
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 201
- Dates: Dec 8, 2022 - Dec 22, 2022 (2 weeks)
- Goal
- Metathesaurus load testing and diagnostic
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Security - create server_error.html
- Unit testing
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 200
- Dates: Nov 28, 2022 - Dec 7, 2022 (2 weeks)
- Goal
- Metathesaurus load testing and diagnostic
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Security - create server_error.html
- Unit testing
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 199
- Dates: Nov 10, 2022 - Nov 23, 2022 (2 weeks)
- Goal
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Security - create server_error.html
- Unit testing
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 198
- Dates: Oct 27, 2022 - Nov 9, 2022 (2 weeks)
- Goal
- LexEVS CTS2 Service deployment
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Security - create server_error.html
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 197
- Dates: Oct 13, 2022 - Oct 26, 2022(2 weeks)
- Goal
- LexEVS Deployment Debugging
- LexEVS CTS2 Service deployment
- EVS Report Exporter update to Vue3
- External support
- Update browsers for Spring 5
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 196
- Dates: Sep 28, 2022 - Oct 12, 2022 (2 weeks)
- Goal
- LexEVS Deployment Debugging
- LexEVS CTS2 Service deployment
- EVS Report Exporter update to Vue3
- EVS Report Exporter Spring update
- External support
- Add HHS Vuln link to EVS Compare
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 195
- Dates: Sep 15, 2022 - Sep 28, 2022 (2 weeks)
- Goal
- LexEVS Deployment Unit testing
- LexEVS CTS2 Service testing
- EVS Report Exporter update to Vue3
- External support
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 194
- Dates: Sep 1, 2022 - Sep 14, 2022 (2 weeks)
- Goal
- LexEVS Deployment Debugging
- LexEVS CTS2 Service deployment
- EVS Report Exporter update to Vue3
- External support
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 193
- Dates: Aug 18, 2022 - Aug 31, 2022 (2 weeks)
- Goal
- LexEVS Deployment Debugging
- LexEVS CTS2 Service update
- External support
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 192
- Dates: July 21, 2022 – Aug 17, 2022 (3 weeks)
- Goal:
- LexEVS Deployment Debugging
- Lexevs CTS2 Service update
- External support
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 191
- Dates: July 5, 2022 – July 20, 2022 (2 weeks)
- Goal:
- CTS2 Framework Spring Update
- Lexevs CTS2 Service update
- Statistics Dashboard
- External support
- Agile Board
- https://tracker.nci.nih.gov/secure/RapidBoard.jspa?rapidView=969&selectedIssue=LEXEVS-5285
Jira server NCI Tracker serverId 7954a81f-12da-3366-a0ef-97c806660e7c key LEXEVSCTS2-426 Jira server NCI Tracker serverId 7954a81f-12da-3366-a0ef-97c806660e7c key CTS2FW-147
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 190
- Dates: June 30, 2022 – July 5, 2022 (2 weeks)
- Goal:
- Spring Update
- Statistics Dashboard
- External support
- Agile Board
- Sprint Report (includes issues/deliverables)
- Pending completion
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 183
- Dates: March 24, 2021 – April 6, 2022 (2 weeks)
- Goal:
- Log4J fix - deploy to Stage/Prod
- LexEVS backlog issues
- Sumo Logic metrics statistics
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 182
- Dates: March 10, 2021 – March 23, 2022 (2 weeks)
- Goal:
- Log4J fix - deploy to Stage/Prod
- LexEVS backlog issues
- Sumo Logic metrics statistics
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 181
- Dates: February 24, 2021 – March 9, 2022 (2 weeks)
- Goal:
- Log4J fix - deploy to Stage/Prod
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 180
- Dates: February 10, 2021 – February 23, 2022 (2 weeks)
- Goal:
- Dashboard move to prod
- Log4J fix - deploy to QA
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- TBD
Sprint 179
- Dates: January 27, 2021 – February 9, 2022 (2 weeks)
- Goal:
- Dashboard move to prod
- Log4J fix - deploy to QA
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 178
- Dates: January 13, 2021 – January 26, 2022 (2 weeks)
- Goal:
- Dashboard move to prod
- Log4J fix
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 177
- Dates: December 30, 2021 – January 12, 2022 (2 weeks)
- Goal:
- Dashboard move to prod
- Log4J fix
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 176
- Dates: December 16, 2021 – December 29, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 175
- Dates: December 2, 2021 – December 15, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 174
- Dates: November 18, 2021 – December 1, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 173
- Dates: November 4, 2021 – November 17, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 172
- Dates: October 21, 2021 – November 3, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 171
- Dates: October 7, 2021 – October 20, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 170
- Dates: September 23, 2021 – October 7, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Compare Tool
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 169
- Dates: September 9, 2021 – September 22, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 168
- Dates: August 26, 2021 – September 8, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 167
- Dates: August 12, 2021 – August 25, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 166
- Dates: July 29, 2021 – August 11, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 165
- Dates: July 15, 2021 – July 28, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 164
- Dates: July 1, 2021 – July 14, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 163
- Dates: June 18, 2021 – June 30, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- LexEVS backlog issues
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 162
- Dates: June 3, 2021 – June 17, 2021 (2 weeks)
- Goal:
- Dashboard investigation and prototyping
- Investigation of Power BI, Logstash
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 161
- Dates: May 20, 2021 – June 2, 2021 (2 weeks)
- Goal:
- QA Support for regression, progression issues
- Dashboard investigation and prototyping
- Investigation of Power BI, Logstash
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 160
- Dates: May 6, 2020 – May 19, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Dashboard investigation and prototyping
- Dashboard consultation and kickoff meeting
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 159
- Dates: April 21, 2020 – May 5, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Dashboard investigation
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 158
- Dates: April 8, 2020 – April 21, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Report Exporter new features
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 157
- Dates: March 25, 2020 – April 7, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Report Exporter new features
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 156
- Dates: March 11, 2020 – March 24, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Report Exporter new features
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 155
- Dates: February 25, 2020 – March 10, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 154
- Dates: February 11, 2020 – February 24, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 153
- Dates: January 28, 2020 – February 10, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 152
- Dates: January 14, 2020 – January 27, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer - deferred downloads
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 151
- Dates: December 31, 2020 – January 13, 2021 (2 weeks)
- Goal:
- Continue Working on Report Explorer - deferred downloads
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 150
- Dates: December 17, 2020 – December 30, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 149
- Dates: December 3, 2020 – December 16, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 148
- Dates: November 19, 2020 – December 2, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- 6.5.4.3.RC2
- 6.5.4.3.RC2 Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.4 branch up to and including 6.5.4.2.FINAL.
- This is a History loader update with the following fix:
- LEXEVS-5019 - OWL2 Loader removes extension from namespace in OWL one Loader
- LEXEVS-5020 - OWL2 Loader does not load rdfs:comments properly into Comment Object
- LEXEVS-5041 - OWL2 Loader doesn't properly handle language designations.
- LEXEVS-5046 - Update selected Loader Scripts to More Reasonable Default Heap Size
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.3.RC2
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/RC2/LexEVS-install-config-6.5.4.3.RC2.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/RC2/LexEVS-install-6.5.4.3.RC2.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/RC2/extLib-6.5.4.3.RC2.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/RC2/lexbig-6.5.4.3.RC2.jar
- Git tag: 6.5.4.3.RC2
- 6.5.4.3.RC2 Build (Java 8/Tomcat 8 build)
Sprint 147
- Dates: November 5, 2020 – November 18, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.3 (loader fixes)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- 6.5.4.3.RC1
- 6.5.4.3.RC1 Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.4 branch up to and including 6.5.4.2.FINAL.
- This is a History loader update with the following fix:
- LEXEVS-4992-Single touch loader script for NCIt
- LEXEVS-4980-Optimize LoadNCIHistory
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.3.RC1
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/LexEVS-install-config-6.5.4.3.RC1.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/LexEVS-install-6.5.4.3.RC1.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/extLib-6.5.4.3.RC1.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.3/lexbig-6.5.4.3.RC1.jar
- Git tag: 6.5.4.3.RC1
- 6.5.4.3.RC1 Build (Java 8/Tomcat 8 build)
Sprint 146
- Dates: October 22, 2020 – November 4, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Build LexEVS 6.5.4.2 (History loader fix)
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- 6.5.4.2.FINAL
- 6.5.4.2.FINAL Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.4 branch up to and including 6.5.4.1.FINAL.
- This is a History loader update with the following fix:
- LEXEVS-4980 Optimize LoadNCIHistory
- LEXEVS-4981 Problem loading history
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.2.FINAL
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.2/Release/LexEVS-install-config-6.5.4.2.FINAL.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.2/Release/LexEVS-install-6.5.4.2.FINAL.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.2/Release/extLib-6.5.4.2.FINAL.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.2/Release/lexbig-6.5.4.2.FINAL.jar
- Git tag: 6.5.4.2.FINAL
- 6.5.4.2.FINAL Build (Java 8/Tomcat 8 build)
Sprint 145
- Dates: October 9, 2020 – October 21, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 144
- Dates: September 24, 2020 – October 8, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 143
- Dates: September 10, 2020 – September 23, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- 6.5.4.1.FINAL
- 6.5.4.1.FINAL Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.4 branch up to and including 6.5.4.FINAL.
- This is a Metathesaurus loader update with the following fix:
- LEXEVS-4966 MetaThesaurus Memory Footprint Adjustment
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.1.FINAL
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.1/Release/LexEVS-install-config-6.5.4.1.FINAL.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.1/Release/LexEVS-install-6.5.4.1.FINAL.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.1/Release/extLib-6.5.4.1.FINAL.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4.1/Release/lexbig-6.5.4.1.FINAL.jar
- Git tag: 6.5.4.1.FINAL
- 6.5.4.1.FINAL Build (Java 8/Tomcat 8 build)
Sprint 142
- Dates: August 27, 2020 – September 9, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 141
- Dates: August 13, 2020 – August 26, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 140
- Dates: July 30, 2020 – August 12, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 139
- Dates: July 16, 2020 – July 29, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 138
- Dates: July 2, 2020 – July 15, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
Sprint 137
- Dates: June 18, 2020 – July 1, 2020 (2 weeks)
- Goal:
- Continue Working on Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- 6.5.4.FINAL
- 6.5.4.FINAL Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.3 branch up to and including 6.5.3.FINAL.
- LexEVS 6.5.4 Release Notes
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.FINAL
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/Release/LexEVS-install-config-6.5.4.FINAL.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/Release/LexEVS-install-6.5.4.FINAL.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/Release/extLib-6.5.4.FINAL.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/Release/lexbig-6.5.4.FINAL.jar
- Git tag: 6.5.4.FINAL
- Lexevs Remote API (v6.5.4 branch)
- Lexevs service (v1.6.4 branch)
- 6.5.4.FINAL Build (Java 8/Tomcat 8 build)
- 6.5.4.RC.2
- 6.5.4.RC.2 Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.3 Release Notes
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.RC.1
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC2/LexEVS-install-config-6.5.4.RC.2.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC2/LexEVS-install-6.5.4.RC.2.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC2/extLib-6.5.4.RC.2.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC2/lexbig-6.5.4.RC.2.jar
- Git tag: 6.5.4.RC.1
- Lexevs Remote API (v6.5.4 branch)
Sprint 136
- Dates: June 4, 2020 – June 17, 2020 (2 weeks)
- Goal:
- Create Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 135
- Dates: May 21, 2020 – June 3, 2020 (2 weeks)
- Goal:
- Create initial Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 134
- Dates: May 7, 2020 – May 20, 2020 (2 weeks)
- Goal:
- Create initial structure and layout for Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 133
- Dates: April 23, 2020 – May 6, 2020 (2 weeks)
- Goal:
- Create Requirements for Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 132
- Dates: April 9, 2020 – April 22, 2020 (2 weeks)
- Goal:
- Build LexEVS Release Candidate
- Create Requirements for Report Explorer
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- 6.5.4.RC.1
- 6.5.4.RC.1 Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.3 Release Notes
- Lexevs API (v6.5.4 branch)
- Git tag: 6.5.4.RC.1
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC1/LexEVS-install-config-6.5.4.RC.1.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC1/LexEVS-install-6.5.4.RC.1.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC1/extLib-6.5.4.RC.1.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.4/RC1/lexbig-6.5.4.RC.1.jar
- Git tag: 6.5.4.RC.1
- Lexevs Remote API (v6.5.4 branch)
- Lexevs service (v1.6.4 branch)
Sprint 131
- Dates: March 26, 2020 – April 8, 2020 (2 weeks)
- Goal:
- Assist with graph db testing on Dev
- Create LexEVS DEV snapshot build for testing
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- SNAPSHOT.DEV.SPRINT131.2020.03.31 Build
- This build includes all LexEVS fix for loader issue:
- LEXEVS-4892 CUI column too narrow.
- Lexevs API (dev branch)
- Git tag: SNAPSHOT.DEV.SPRINT131.2020.03.31
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/LexEVS-install-config-SNAPSHOT.DEV.SPRINT131.2020.03.31.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/LexEVS-install-SNAPSHOT.DEV.SPRINT131.2020.03.31.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/extLib-SNAPSHOT.DEV.SPRINT131.2020.03.31.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/lexbig-SNAPSHOT.DEV.SPRINT131.2020.03.31.jar
- Git tag: SNAPSHOT.DEV.SPRINT131.2020.03.31
- This build includes all LexEVS fix for loader issue:
Sprint 130
- Dates: March 12, 2020 – March 25, 2020 (2 weeks)
- Goal:
- Assist with graph db testing on Dev
- Create LexEVS DEV snapshot build for testing
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- SNAPSHOT.DEV.SPRINT130.2020.03.12 Build
- This build includes all LexEVS updates.
- Lexevs API (dev branch)
- Git tag: SNAPSHOT.DEV.SPRINT130.2020.03.12
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/LexEVS-install-config-SNAPSHOT.DEV.SPRINT130.2020.03.12.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/LexEVS-install-SNAPSHOT.DEV.SPRINT130.2020.03.12.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/extLib-SNAPSHOT.DEV.SPRINT130.2020.03.12.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/lexbig-SNAPSHOT.DEV.SPRINT130.2020.03.12.jar
- Git tag: SNAPSHOT.DEV.SPRINT130.2020.03.12
- Lexevs REMOTE API (dev branch)
- Git tag: SNAPSHOT.DEV.SPRINT130.2020.03.12
Sprint 129
- Dates: February 26, 2020 – March 11, 2020 (2 weeks)
- Goal:
- Assist with graph db testing on Dev
- Prepare for LexEVS release
- Provide continued support and issue resolution
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 128
- Dates: February 13, 2020 – February 26, 2020 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 127
- Dates: January 30, 2019 – February 12, 2020 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
Sprint 126
- Dates: January 16, 2019 – January 29, 2020 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- TBD
- Artifacts
- SNAPSHOT.DEV.SPRINT126.2020.01.28 Build
- This build includes all graph resolve updates.
- Lexevs API (dev branch)
- Git tag: SNAPSHOT.DEV.SPRINT126.2020.01.28
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/LexEVS-install-config-SNAPSHOT.DEV.SPRINT126.2020.01.28.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/LexEVS-install-SNAPSHOT.DEV.SPRINT126.2020.01.28.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/extLib-SNAPSHOT.DEV.SPRINT126.2020.01.28.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/Dev/lexbig-SNAPSHOT.DEV.SPRINT126.2020.01.28.jar
- Git tag: SNAPSHOT.DEV.SPRINT126.2020.01.28
- Graph Resolve (dev branch)
- Git tag: SNAPSHOT.DEV.SPRINT126.2020.01.28
Sprint 125
- Dates: January 2, 2019 – January 15, 2020 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 124
- Dates: December 19, 2019 – January 1, 2020 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 123
- Dates: December 5, 2019 – December 18, 2019 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 122
- Dates: November 21, 2019 – December 4, 2019 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 121
- Dates: November 7, 2019 – November 20, 2019 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 120
- Dates: October 24, 2019 – November 6, 2019 (2 weeks)
- Goal:
- Implement new hybrid text query/association API
- Add graph db tests to Jenkins
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 119
- Dates: October 10, 2019 – October 23, 2019 (2 weeks)
- Goal:
- Assist moving LexEVS 6.5.3 up to Stage/Prod
- Implement new hybrid text query/association API
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 118
- Dates: September 25, 2019 – October 9, 2019 (2 weeks)
- Goal:
- Assist moving LexEVS 6.5.3 up to Stage/Prod
- Implement new hybrid text query/association API
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
Sprint 117
- Dates: September 12, 2018 – September 25, 2019 (2 weeks)
- Goal:
- Investigate Metathesaurus
- Assist QA with testing
- Implement new hybrid text query/association API
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- Artifacts
- 6.5.3.FINAL
- 6.5.3.FINAL Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.2 branch up to and including 6.5.2.FINAL.
- LexEVS 6.5.3 Release Notes
- Lexevs API (v6.5.3 branch)
- Git tag: 6.5.3.FINAL
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/Release/LexEVS-install-config-6.5.3.FINAL.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/Release/LexEVS-install-6.5.3.FINAL.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/Release/extLib-6.5.3.FINAL.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/Release/lexbig-6.5.3.FINAL.jar
- Git tag: 6.5.3.FINAL
- Lexevs Remote API (v6.5.2 branch)
- Lexevs service (v1.6.3 branch)
- URI Resolver (v1.1.1 branch)
- 6.5.3.FINAL Build (Java 8/Tomcat 8 build)
Sprint 116
- Dates: August 29, 2018 – September 11, 2019 (2 weeks)
- Goal:
- DevOps - 6.5.3 release documentation
- Assist QA with testing
- Implement new hybrid text query/association API
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- Artifacts
Sprint 115
- Dates: August 15, 2018 – August 28, 2019 (2 weeks)
- Goal:
- DevOps - 6.5.3 release documentation
- Assist QA with testing
- Investigate new hybrid text query/association API
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- Artifacts
- 6.5.3.RC.3
- 6.5.3.RC.3 Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.2 Release Notes - Not Released
- Lexevs API (v6.5.3 branch)
- Git tag: SNAPSHOT TBD
- Git tag: 6.5.3.RC.4
- Test code only
- https://github.com/lexevs/lexevs-remote/tree/6.5.3.RC.4
- Lexevs service (v1.6.3 branch)
Sprint 114
- Dates: August 1, 2018 – August 14, 2019 (2 weeks)
- Goal:
- DevOps - Dockerize LexEVS
- Assist QA with testing
- QA reported issue work
- Provide continued support and issue resolution.
- Agile Board
- Sprint Report (includes issues/deliverables)
- Retrospective
- Artifacts
- 6.5.3.RC.3
- 6.5.3.RC.3 Build (Java 8/Tomcat 8 build)
- This build includes all changes from the LexEVS 6.5.2 Release Notes - Not Released
- Lexevs API (v6.5.3 branch)
- Git tag: 6.5.3.RC.3
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/RC3/LexEVS-install-config-6.5.3.RC.3.xml
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/RC3/LexEVS-install-6.5.3.RC.3.jar
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/RC3/extLib-6.5.3.RC.3.zip
- https://cbiit-download.nci.nih.gov/evs/LexEVS/v6.5/6.5.3/RC3/lexbig-6.5.3.RC.3.jar
- Git tag: 6.5.3.RC.3
- Lexevs Remote API (v6.5.3 branch)
- Lexevs service (v1.6.3 branch)
...