Sprint Status

 

Current Sprint  Sprint 42 (October 27, 2016 – November 9, 2016)

16X237 Agile Development - Sprint Status#16X237AgileDevelopment-SprintStatus-Sprint42

Looking forward to Sprint 43, this is what we anticipate working on:

  • Finalize Java 1.8 builds and test
  • Three GUI issues
  • Two CLI issues (These are more important than the GUI issues)
  • Team prep for F2F meeting
Migration to MySQL 5.6

Discussion Points:

  • Oracle doesn't support 5.5 anymore. 
  • We should start pursuing upgrading to 5.6.
  • MariaDB will be supported in 2017.  We may consider going directly to this instead of MySQL 5.6.
  • We should consider if thereMariaDB should be coupled with CentOS7.

Decision Points:

6.4.1.2 Build and Deployment

  • Status

Discussion Points:

  • Jira
    serverNCI Tracker
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId7954a81f-12da-3366-a0ef-97c806660e7c
    keyLEXEVS-2413
  • Installed on QA and passed app scan
  • Waiting for the term browser to pass the app scan

Decision Points:

6.4.1.3 Build and Deployment

  • Status

Discussion Points:

  • Jira
    serverNCI Tracker
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId7954a81f-12da-3366-a0ef-97c806660e7c
    keyLEXEVS-2448
  • This is a loader change.
  • This is installed on DATA-DEV.  Rob hasn't had a chance yet to test it.

Decision Points:

NCI Nexus Server Migration Update

Discussion Points:

  • Mayo Infromatics Nexus server is shutdown

Decision Points:

CTS2 URLs for 6.3 and 6.4

Discussion Points:

  • CTRP has tested the 6.4 URLs successfully
  • When will the 6.4 https URLs be set as the default URL?
    • We should first have the http url forwarded to the https URLs.

Decision Points:

  • Tracy/Jason will create a ticket to have the http URLs forwarded to https.
DEV deployment process

Discussion Points:

  • We need to request that Jacob set up a VM for the dev team to push out snapshot releases.

Decision Points:

F2F Planning

Discussion Points:

Decision Points:

LexEVS External UsersNo updates.
Team Absences

Mayo Team

  • Cory - Nov 23 - 25
  • Scott - Nov 23 - 25
  • Craig - Nov 11 - 16, Nov 23 - 25

NCI

  • Tracy
    • Dec 14-16
    • Jan 9-17
    • Feb 21-24
  • Rob
    • 11/14 – PM only

    • 11/24-11/28

    • 12/9

    • 12/19

    • 12/23-12/27

    • 1/2/2017

...