Sprint Status

 

Current Sprint  Sprint 43 (November 10, 2016 – November 23, 2016)

16X237 Agile Development - Sprint Status#16X237AgileDevelopment-SprintStatus-Sprint43

  • We have done code development work the first week.
  • We will switch gears to prep for the F2F the second part half of this sprint.
Migration to MySQL 5.6

Discussion Points:

  • We found that our Docker test scripts were running MySQL 5.7.  Everything runs fine here. 
  • We also retested using 5.5 successfully.
  • We will do some MySQL 5.6 testing as time permits.
  • We asked if there is a timeline to upgrade to MySQL 5.6?

Decision Points:

  • Add We added this to the F2F Agenda
Decision Points:
  • .

6.4.1.2 Build and Deployment

  • Status

Discussion Points:

  • Jira
    serverNCI Tracker
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId7954a81f-12da-3366-a0ef-97c806660e7c
    keyLEXEVS-2413
  • This and the term browser have now passed the app scan.
  • This could possibly go up to PROD in the next week.

Decision Points:

  • We will need to push 6.4.1.2 to the NCIP channel.
  • The Mayo team will need to verify that the client is backwards compatible (6.4.1.2 and 6.4.1)

6.4.1.3 Build and Deployment

  • Status

Discussion Points:

  • Jira
    serverNCI Tracker
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId7954a81f-12da-3366-a0ef-97c806660e7c
    keyLEXEVS-2448
  • This is a loader change.
  • 6.4.1.4 will have valueset fixes.

Decision Points:

NCI Nexus Server Migration Update

Discussion Points:

  • Working on the maven publish script and authorization issues.

Decision Points:

BioMarker Discussion

Discussion Points:

  • This is present in the MetathasaurusMetathesaurus.
  • Need to implement a new semantic type
  • Some concepts have multiple semantic types.

Decision Points:

  • Scott to create a JIRA item to track this issue.

Valueset load -

  • Added feature to tag
  • Added feature to set version

Discussion Points:

  • This code should be available in the next week.

Decision Points:

CTS2 URLs for 6.3 and 6.4

Discussion Points:

Decision Points:

  • Tracy will create a ticket to have Jacob do this.
  • Will Jacob will start on DEV and work up the tiers.

Triplestore evaluation meeting (Tuesday)

  • Review

Discussion Points:

  • No further discussion necessary.

Decision Points:

F2F Planning

Discussion Points:

Decision Points:

  • Time  Larry suggested start/stop time  9:00 - 4:30
    • We can have other meetings before/after these times if it works for the teams meeting.
        
    • There is maintenance
    • Maintenance on the red line metro  
  • Rob is out Wednesday.
  • User Group Discussion - combine? or Drop?  Larry suggested the following:
    • GCD won't be ready
    • caDSR nothing to discuss with this release
    • CTRP (clinical trial API) may be interested in a REST discussion.
      • transitive closure
      • defining associations beyond descendants and ancestors
  • Consolidate the REST API meetings to 2 hours
  • OWL and RRF Mapping Discussion - can drop to 1 hour
LexEVS External Users 
Team Absences

Mayo Team

  • Cory - Nov 23 - 25
  • Scott - Nov 23 - 25
  • Craig - Nov 11 - 16, Nov 23 - 25

NCI

  • Tracy
    • Dec 14-16
    • Jan 9-17
    • Feb 21-24
  • Rob
    • 11/24-11/28

    • 12/9

    • 12/19

    • 12/23-12/27

    • 1/2/2017

...