Spring Related Update | Estimated Effort | Status | |
---|---|---|---|
Spring Related Update | Estimated Effort | Status | |
Ivy Dependency Update | 3 days | Complete | |
Ibatis to Mybatis xml conversion | 3 days | Complete | |
Compile capable code conversion | 3 days | Complete | |
Application context startup | 1 week | Complete | |
CodingSchemeDao Verification tests / Code Corrections | 10 days | Complete | |
Association Dao Verification tests / Code Corrections | 10 days | Complete | |
Registry Dao Verification / Code Corrections | 10 days | Complete | |
Coded Node Graph Dao / Code Corrections | 10 days | Complete | |
Entity Dao / Code Corrections | 10 days | Complete | |
NCI History Dao / Code Corrections | 3 days | Complete | |
Property Dao / Code Corrections | 10 days | Complete | |
Revision Dao / Code Corrections | 2 days | In Progress | |
System Release Dao / Code Corrections | 1 day | Complete | |
Pick List Dao / Code Corrections | 1 week | Not Started | |
Pick List Entry Dao / Code Corrections | 1 week | Not Started | |
Source Asserted Value Set Dao / Code Corrections | 2 days | Complete | |
Value Set Definitions Dao / Code Corrections | 10 days | Complete | |
Value set Hierarchy Dao / Code Corrections | 1 day | Complete | |
Vaue set Definition Entry Dao / Code Corrections | 2 days | Complete | |
Value Set Entry State Dao / Code Corrections | 2 days | Complete | |
Value Set Property Dao / Code Corrections | 1 week | Complete | |
Versions Dao / Code Corrections | 2 days | In Progress | |
Testing/ Verification | 1 week | Not Started2 weeks | In Progress |
Load tests | 2 weeks | In Progress | |
Testing verification Recoding | 10 days | In Progress | |
Full system test | 1 day | Not Started | |
LexEVS Remote | 3-4 weeks | Not Started | |
LexEVS CTS2 Service | 2-3 weeks | In progress | |
Total Effort (Approximately) | 4-5 months |
...