SYSTEMS
Systems

Discussion Points:

  • Jenkins having issues running Java8
    • Will be pushed harder this year - 
    • EOL Sep '23
  • Status of migration on new QA tier.
    • Met last week, all known issues now fixed
  • Stage migration status
  • Systems contract changing vendors in January 2023
    • Some personnel changes expected
    • Migration plan

Decision Points:


LEXEVS UPDATES

LexEVS Sprint Status


  • LexEVS CTS2 Service - on QA - config fixed last week. Waiting on testing
  • Report Exporter - On QA, tests passed. Need app scan
  • Vue3 Updates for Report Exporter 
  • Working on updating browser for Spring 5 - on dev
Future Planning

Discussion Points:

 Planning for Mayo team in the coming fiscal year:

  • Java 8 implications
    • Do code inventory for Java migration
      • Work started - may take 2 weeks
      • Painful for lucene update
  • Would like to see this in a checklist, similar to Spring 5 chart (below)
    • Should include a schedule.

CTS2 Mapping/URI Resolver

Discussion Points:

  • Configuration fix. Needs testing

Decision Points:

caDSR Query

Review requirements for caDSR query

  • They have been provided a flat file for NCIt
    • Adding a new column to End of December version
  • All questions about NCIt and other vocabularies should include Lyubov, Jason, Lori and Mark, and limited people beyond that.

Statistics Dashboard

Discussion Points: 

Decision Points:

Comparison/Mapping Tool

Discussion Points:

  • March timeframe

Decision Points:

EVS transition to virtual machines

Discussion Points:

  • Server Migration 2021
    • QA
      • Meeting last week resolved config issues
      • Needs URLs repointed
    • Stage 
      • Instance of VM instantiated. Needs configuration

Decision Points:

Report Exporter

Discussion Points:

  • Tomcat and Spring Vulnerability noted on the Report Exporter
  • Working on update to Vue3 (JavaScript Framework).
    • ~ 2 month - on week 7 of estimated 8 -
      • delayed due to high priority white label error work 
      • 3 different phases
        • Dependencies updated - complete
        • Squashing errors generated from update - complete?
        • Unit testing
          • bug squashing from this
    • Look at updating to Java 11

Decision Points:

AWS Cloud to be in Separate Account

Discussion Points

  • No Response as of yet

Decision Points:

Team Absences


Mayo Team - 

MSC - Jason out Christmas week

Leidos -

Systems - Tracy Truong out this week


EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

Discussion Points:

Decision Points:


DATA UPDATES
Data

Discussion Points: 

  • NCIt for Dec 22 exported
  • Flat file has new column

Decision Points:


BROWSER UPDATES

Browser

Discussion Points:

  • No updates this week

Decision Points: 


QA UPDATES

QA

Discussion Points:  (see chart)

  • Data regression - on prem
  • Data - progression and regression for Dec 2022 to be done for AWS
  • Report exporter - testing done

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 

Mark Benson TPM Update
  • Compiling post-mortem report

...