LexEVS Spring Migration Progress


Technical Debt Related Update

Estimated Effort

Start Date

Complete Date

Status

ADO Ticket

Code Inventory4 days

Complete2037998
Lexevs - update "easy" jars2 days

Complete2111723
Update ddlutils - research and design3 days

Complete2122958
Update ddltils - implementations10 days

In Progress2141127
Lexevs Unit testing2 days


2141156
CTS2 lexevs-service vulnerability update2 days


2141189
CTS2 unit testing2 days


2141198
QA Lexevs / CTS2

3 days




2141217
Repair QA issues2 days



Deployment Lexevs / CTS25 days (elapsed)


2141227
Update LexEVS to Java 11 - research and design4 days


2152899
LexEVS Java 11 implementation5 days


2152917
lucene 9 - research and design8 days


2145025
lucene 9 - implementation15 days


2145027
LexEVS Java 11 unit testing3 days


2152921
CTS2 lexevs-service Java 11 - research and design 3 days


2152928
CTS2 lexevs-service Java 11 implementation3 days


2152932
CTS2 unit testing2 days


2152941
QA Lexevs / CTS2

3 days




2152945
Repair QA issues2 days


2153023
Update Jenkins1 day


2152947
Deployment Lexevs / CTS210 days (elapsed)


2152950
lexevs-service-rest-docs vulnerability update design2 days



lexevs-service-rest-docs vulnerability implementation4 days



lexevs-service-rest-docs unit testing1 day



lexevs-service-rest-docs QA

1 day





lexevs-service-rest-docs deployment4 days (elapsed)



lexevs-service-rest-docs Java 11 design

2 days





lexevs-service-rest-docs Java 11 implementation3 days



lexevs-service-rest-docs unit testing1 day



lexevs-service-rest-docs QA

1 day





lexevs-system-test design4 days



lexevs-system-test implementation6 days



lexevs remaining dependency updates - design10 days



lexevs remaining dependency updates - implementation20 days



CTS2 remaining dependency updates - design1 day



CTS2 remaining dependency updates - implementation3 days



Unit testing2 days



QA2 days



Deployment5 days (elapsed)



Total Effort (Approximately)104 days



Technical Debt Related Update

Estimated Effort

Status

Report Exporter vulnerabilities - design4 days
Report Exporter vulnerabilities - implementation5 days
Unit testing2 days
QA2 days
Deployment5 days (elapsed)

...