NIH | National Cancer Institute | NCI Wiki  

Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Add Jira column to table

...

LexEVS Spring Migration Progress


Technical Debt Related Update

Estimated Effort

Start Date

Complete Date

Status

JIRA

ADO Ticket

Code Inventory4 days12/20/221/30/23Complete
2037998
Lexevs - update "easy" jars2 days1/31/232/13/23Complete
2111723
Update ddlutils - research and design3 days2/2/232/15/23Complete
2122958
Update ddltils - implementations10 days2/15/233/8/23Complete
2141127
Lexevs Unit testing2 days3/8/2023
In ProgressLEXEVS-53252141156
CTS2 lexevs-service vulnerability update2 days3/13/20233/20/23Complete
2141189
CTS2 unit testing2 days3/20/23
In ProgressLEXEVS-53262141198
QA Lexevs / CTS2

3 days




LEXEVS-53272141217
Repair QA issues2 days




Deployment Lexevs / CTS25 days (elapsed)



2141227
Update LexEVS to Java 11 - research and design4 days



2152899
LexEVS Java 11 implementation5 days



2152917
lucene 9 - research and design8 days



2145025
lucene 9 - implementation15 days



2145027
LexEVS Java 11 unit testing3 days



2152921
CTS2 lexevs-service Java 11 - research and design 3 days



2152928
CTS2 lexevs-service Java 11 implementation3 days



2152932
CTS2 unit testing2 days



2152941
QA Lexevs / CTS2

3 days





2152945
Repair QA issues2 days



2153023
Update Jenkins1 day



2152947
Deployment Lexevs / CTS210 days (elapsed)



2152950
lexevs-service-rest-docs vulnerability update design2 days




lexevs-service-rest-docs vulnerability implementation4 days




lexevs-service-rest-docs unit testing1 day




lexevs-service-rest-docs QA

1 day






lexevs-service-rest-docs deployment4 days (elapsed)




lexevs-service-rest-docs Java 11 design

2 days






lexevs-service-rest-docs Java 11 implementation3 days




lexevs-service-rest-docs unit testing1 day




lexevs-service-rest-docs QA

1 day






lexevs-system-test design4 days




lexevs-system-test implementation6 days




lexevs remaining dependency updates - design10 days




lexevs remaining dependency updates - implementation20 days




CTS2 remaining dependency updates - design1 day




CTS2 remaining dependency updates - implementation3 days




Unit testing2 days




QA2 days




Deployment5 days (elapsed)




Total Effort (Approximately)104 days




Technical Debt Related Update

Estimated Effort

Status

Report Exporter vulnerabilities - design4 days
Report Exporter vulnerabilities - implementation5 days
Unit testing2 days
QA2 days
Deployment5 days (elapsed)

...