Systems

See ticket chart (above)



LEXEVS UPDATES
Future Planning

Planning for April - EVS Plans for April 2023.png

  • Priorities and Goals for April are
    • Complete Report Exporter Update from Vue2 → 3
    • Phase 1 passed QA, to be moved to Stage
    • Phase 2 on dev
    • Test Java 8 migration to Corretto - being tested on Dev
    • Write and review Comparison Mapping Tool User Stories and Requirements - under development
    • Review Devops and Communication channels and needs - under development
    • Proposal for "Health" dashboard for EVS infrastructure - under development

LexEVS Sprint Status


  • Report Exporter on QA
  • Working on updating ncitbrowser for Spring 5 - on dev -  https://ncit-dev.nci.nih.gov
    • Tentatively complete - doing testing
    • Metathesaurus browser to come
  • LexEVS/CTS2 phase 1 on Stage
    • Unit testing successful
    • Stage passed, requested to Prod
  • Phase 2 on Dev
Technical Debt remediation

LexEVS Code Debt Refactoring

caDSR Query

Discussion Points:

  • caDSR bringing up a new service, so there will be some URL changes to point to this. - NCIt browser ready on Stage and waiting on them.
  • SIP working with GDC to update links

Statistics Dashboard

Discussion Points: 

  • Google analytics - Retiring GA and going to GA4
      • EVSExplore
      • NCI Terms Browser - On Stage, waiting on caDSR
  • Statistics - Sumo Logic
    • Analyzing Sumo, considering other vendors (Datadog, others?)

Decision Points:

Comparison/Mapping Tool

Plan is to update product roadmap by end of April.

Mark is working on user stories and requirements

EVS transition to virtual machines

Status:

  • We are waiting to hear from Systems on who will be doing next set of work
  • Chuck shared an email about the work that he did for EVS
  • Aaron Taye attended 4/26 and discussed the plan moving forward. AT is project manager and will be coordinating team.
    • Chuck on team as historical SME, but not the primary tech
    • Zihua He will be primary documentation
    • Eric Guava will be hands-on tech

Reference: Wiki page: Server Migration 2021


Report Exporter
  • Discussion Points:

    • Working on update to Vue3 (JavaScript Framework). EVSREPEXP-451
      • master ticket: EVSREPEXP-442 - Migrate Vue.js version from 2.0 to 3.0
      • Description
        • On QA and being tested
          • Duplicate items in list box - app.js, being investigated
    • Vulnerable dependencies
    • Demo wanted in the near future - this month
    • Java vulnerability reported 5.1.23, requires systems to update java version on VM. NCI-SCTASK0644391. 

    Decision Points:

AWS Cloud to be in Separate Account

Discussion Points

  • Frozen

Decision Points:

Team Absences


Mayo Team - Andrew - April 27 - May 2

MSC -

Leidos -

Systems - 


EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group

Discussion Points:

  • Browser hand-off planning discussions
  • Mayo to notify when on Dev

Decision Points:


DATA UPDATES
Data

Discussion Points: 

Decision Points:


BROWSER UPDATES

Browser


  • caDSR new tool - CDE browser links to terms browser.  URLs needed updating and promoted in concert with CDE Browser
    • Ready for Stage
    • Will hold on Stage until CDE browser is ready to go to Prod



QA UPDATES

QA

Discussion Points:  (see chart)

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 

Mark Benson TPM Update
  • EVS Explore/Rest API ATO being worked upon

...