Ticket Description Actions, Update

NCI-RITM0512149

Security consult about IP traffic to Prod
Asked for dynamic IP throttling
Working to escalate using WAF (Web Application Firewall)
Mark to keep close eye on this


NCI-RITM0528879Install Tomcat9 deployment track for ncitermform to evs-jenkins
Elevated on 5/29. Will contactContacted systems directly.  Still waiting



EVS transition to virtual machines

STATUS:

  • Tomcat 8.5 reached EoL - needing new stacks for all tiers
    • Oracles OES8, Tomcat 10, Java 17 
      • Java 17 implemented
      • Others to follow once 17 on Pro
    • Options
      • Tomcat 9 and Java 17 installed on Dev
      • evs-jenkins working for NCItBrowser and lexevscts2
      • OES8 could come later
    • NCItermform installed on Dev - needs testing
  • Tomcat 9 installed on Dev.  
    • Recoding for NCIm complete
    • NCI Term Form Jenkins requested
    • NCIm on Dev and ready for testing
      • Preparing for promotion to QA
      • Waiting on Jenkins?
  • Should get started on QA
    • Deployment tracks requested in Jenkins





LEXEVS UPDATES

Monthly Planning and Focus

Completed Sprint - Sprint 220 (May 13 - May 31) - 

Current Sprint  - Sprint 221 (June 07 - July 08) - 

For the month of June 2024

Report Exporter
  • Working on templating starting
    • Doing phase 1 - moved to Stage
      • Stage EVS Rest API having issues
      • Cloud team addressing the issue
    • In progress: implement file-based template storage
      • Code completed
      • Tomcat 9 testing on QA
      • Systems working on implementing Stage and Prod


Security

Tomcat 8.5 is EOL - risk if new vulnerability discovered

  • Oracle Java 8 - still being used on DataQA
    • Still present on other servers, in $PATH
    • Java 17 being added next week
    • Current proposal is to not push to DataQA, let it retire
  • Need to check on Processing Server
  • FTP1 has .bash_history file
    • Was removed from Dev but needs removal on Prod 
    • Mark to do rsync this week to fix this issue on Prod

Statistics Dashboard

OBJECTIVE 
Build scheduled report  report  - Discovered not available on gov cloud. Will need to come up with operational procedure

STATUS

  • All May logs loaded from Sumo
    • Fixing malformed logs
Comparison/Mapping Tool

Request put in for retirement - no response yet

AWS Cloud to be in Separate Account

Waiting on AWS teamSystems working on this

Team Absences


Mayo Team - Andrew June 17 -23,  Scott off July 1-8, Tracy July 4,5

MSC - Jason, June 17th → 21st 

Leidos - Chao July 4-July 22nd

QA - 

Gov -  Lyubov June 27-July 6, Back July 9



EVS SERVICE AND ARCHITECTURE GROUP UPDATES
EVS Service and Architecture Group


LexEVS Retirement




DATA UPDATES
Data

BROWSER UPDATES

Browser
  •  

QA UPDATES

QA

TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Mark Benson TPM Update
  • Call for people to complete their required trainings.
    • Security
    • Implicit bias
  • FTP1 instance may need to be rebooted - need to schedule time with users




...