NIH | National Cancer Institute | NCI Wiki  

Error rendering macro 'rw-search'

null

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 5 Next »

A calculated date, by default. The system calculates this date as follows:

  • If the trial has any reactivation dates, the system starts with the most recent one.
  • Otherwise, the system starts with the submission date.
  • The system adds ten business days.
  • The system adds any number of days in which trial was on hold waiting for information from the submitter. (If the trial has any reactivation dates, the system considers only days on hold since the most recent reactivation date.)
  • The system requires this date to fall on a business day.

(A business day is any weekday that is not a Federal holiday. For a list of Federal holidays, refer to the U.S. Office of Personnel Management's list of Federal Holidays.)

If the date has an underline, a Super Abstractor has overridden the default date for the trial.

  • No labels