Sprint Date
-
Sprint Goals
- 2022 Q1 Production Release
- Hot Fixes
- Implement new landing page design
- Integrate GraphiQL application
- Create a hyperlink for software release notes
Sprint 12 Jira Issue Types
Software Release Information
Date | Build Type | Semantic Version | Jenkins Build | Front-End Tag | Back-End Tag |
---|---|---|---|---|---|
| Production Release Candidate | 3.8.1 | 576 | 3.8.1-{rc-576} | 4.0.1-{576} |
| Production Release Candidate | 3.8.2 | 577 | 3.8.2-{rc-577} | 4.0.1-{577} |
| Production Release Candidate | 3.8.3 | 581 | 3.8.3-{rc-581} | 4.0.1-{581} |
| Production Release Candidate | 3.8.4 | 582 | 3.8.4-{rc-582} | 4.0.1-{582} |
| Production Release Candidate | 3.8.5 | 583 | 3.8.5-{beta-583} | 4.0.1-{583} |
| Production Release Candidate | 3.8.6 | 584 | 3.8.6-{beta-584} | 4.0.1-{584} |
| Production Release Candidate | 3.8.7 | 586 | 3.8.7-{rc-586} | 4.0.1-{586} |
| Production Release Candidate | 3.8.7 | 588 | 3.8.7-{rc-588} | 4.0.2-{588} |
| Internal Beta Release | 3.9.0 | 591 | 3.9.1-{rc-591} | 4.0.2-{591} |
| Internal Beta Release | x.y.z | x.y.z-{beta-build} | 4.0.1-{build} |
Hot Fixes
Sprint Schedule
Date | Scrum Ceremony | Purpose |
---|---|---|
| Sprint Kickoff | Initiate sprint 12 |
| Code Freeze | No new code will be pushed to the build intended for the production release at close of business |
| Q1 2022 Production Release | Quarterly software release to production environment |
| Sprint 13 Pre-planning | Review tasks targeted for next sprint and identify clarifications needed, apply initial story point estimations and initial projected assignees |
| Sprint 13 Planning | Review prioritized tasks, assert assigned stories, assert final story point estimations, review story points by assignee |
| Review & Retrospective | Demo work completed, discuss what went well and what can be improved |