Attendees

NameRolePresent
Haber, MargaretNIH/NCI
x
Fragoso, Gilberto NIH/NCI     

De Coronado, Sherri    

NIH/NCI   x

Safran, Tracy

NIH/NCI [C]x
Ong, Kim L
ISx
Lucas, Jason R
ISx
Bauer, Scott  Mayox
Stancl, Craig
Mayox
Endle,  CoryMayox
Wynne, Robert    NIH/NCI [C] 

Kuntipuram, Kumar

NIH/NCI [C] 
Mensah, JacobNIH/NCI [C]x
Trong, TracyNIH/NCI [C] 
Vinayagampudur, Kiruthika
NIH/NCI [C] 
Kisler, BronNIH/NCI [C]x
Remennik, LyubovNIH/CC/BTRISx

Action Items

AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus
      

Agenda

EVS Weekly Tech Meeting

Discussion Points:

  • LexEVS
    • Lexevs 6.5 AnthillPro migration to Jenkins update
      • The Jenkins workflow on Dev is created. 
      • Mayo team to review.
    • CTS2 WSDLs - failing to start up issue
      • CTS2 service update has been deployed to Prod.
  • Browser/Tools
  • Data
  • Systems
  • Triple Store/EVS API

Decision Points:

Roll Call 

Sprint Status

 

Current Sprint  Sprint 79 (March 29, 2018 – April 11, 2018)

16X237 Agile Development - Sprint Status#16X237AgileDevelopment-SprintStatus-Sprint79

EVS Technical Strategy Meeting/Discussion Update

Discussion Points:

  • Meeting was cancelled for this week.

Decision Points:

Release Roadmap
  • Discussion Points:
    • Planned Release Roadmap
      • Remote API (done)
      • Remove external dependencies from informatics.mayo.edu
      • Remove external SOAP dependencies from OMG - WSDL (done) 
      • Remove external dependencies from OMG - XSD  
      • Asserted Value Set work
        • Asserted Value Sets to be included in Search (done)
        • Non-Asserted Value Sets to be included in search (done)
        • Non-Asserted Value Sets to be included in hierarchy (3517, 3509)
        • Value Set URI and name included in resolved concept reference returned by search (done)
      • Additional JIRA Backlog Items (to be included in the release):


      • Estimated effort:
        • Sprint 78 - Complete
        • Sprint 79 - Complete
        • Sprint 80 - April
        • Sprint 81 - May
        • Sprint 82 - May
        • Sprint 83 - June -> on QA

Decision Points:

Export OWL RDF issue

Discussion Points:

  • It would be helpful to have a use case to understand what the requirements
  • This may be significant effort to make this work.

Decision Points:

  • Hold off on any work until we determine more requirements.
Tree Extension - Name space issue

Discussion Points:

  • Kim suggested that the priority is high as he has a fix, but it may affect performance.
  • Mayo team will investigate the issue.

Decision Points:

Possible EVS F2F Dates (Summer)

Discussion Points:

  • Proposed dates: July 18 and 19.

Decision Points:

LexEVS External Users

Discussion Points:

Decision Points:

Team Absences

Mayo Team

  • Cory - June 1
  • Scott - April 20, June 19th - July 1st, July 25 -27
  • Craig -

NCI

  • Tracy -
  • Rob - 
  • Bron -
  • Sana -
  • Kim -
  • Kiruthika -

JIRA Issues

Recent LexEVS Related Bugs and Features (within last week)

Recent CTS2 Service Related Issues (within last week)

6.5 LexEVS Related Issues

6.5 CTS2 Service Related Issues

Project Plan Changes

#DescriptionDue DateResourcesNotesRisksMitigation
 None     
       
       

 Planned Activities

Area of InterestDetails
  
  
  

Risks, Issues, Dependencies

Risks

Opened DateDue DateDescriptionLikelihood (H, M, L)ImpactAssignedStatusMitigation Strategy
         
         

Issues

 #Opened DateDescriptionImpactAssignedStatus
      
      
      

Dependencies

Opened DateDescriptionAssigned
   
   

 

Action Item Backlog

 #AssignedDescriptionDate IdentifiedDue DateDate CompletedStatus