Sprint Date
-
Sprint Goals
- Fix resolution of ICDC studies on identifiers.org
- Improve handling of study-level files
- Build a UI for an interactive data model/data dictionary viewer using Windmill
- Complete Design QA review across study, case, program, and cart-centric views
Sprint 8 Issues (n = 39)
Software Build Information
Date | Build | Front-End Tag | Back-End Tag |
---|---|---|---|
| TBD | 3.2.1-{beta-513} | 4.0.1-{513} |
| TBD | 3.3.0-{beta-520} | 4.0.1-{520} |
| TBD | 3.3.1-{beta-521} | 4.0.1-{521} |
Sprint Schedule
Date | Scrum Ceremony | Purpose |
---|---|---|
| Sprint Kickoff | Initiate a new sprint |
| Sprint 9 Pre-planning | Review tasks targeted for next sprint and identify clarifications needed, apply initial story point estimations and initial projected assignees |
| Sprint 9 Planning | Review prioritized tasks, assert assigned stories, assert final story point estimations, review story points by assignee |
Review & Retrospective | Demo work completed, discuss what went well and what can be improved |
Completed in Sprint 8