Attendees

NameRolePresent
Remennik, LyubovNIH/NCIx

Safran, Tracy

NIH/NCI [C]
Ong, Kim LISx
Lucas, Jason RISx
Bauer, Scott  Mayox
Stancl, CraigMayox
Endle,  CoryMayox

Kuntipuram, Kumar

NIH/NCI [C]x
Solie, ChuckNIH/NCI [C]x
Trikha, AkhileshNIH/NCI [C]
Trong, TracyNIH/NCI [C]
Kondareddy, SwathiNIH/NCI [C]x
Singh, ItendraNIH/NCI [C]x
Yang, ChenNIH/NCI [C]x
Johnson, ConnieNIH/NCI [C]x
Whiteman, LoriNIH/NCI [C]

Agenda

EVS Discussion


SYSTEMS
Systems

Discussion Points:

Decision Points:


LEXEVS UPDATES

LexEVS Sprint Status


Current Sprint - Sprint 156 (March 11, 2020 – March 24, 2020)

16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint156

Activities
  • Report Exporter is on Prod (behind firewall).
  • Work progressing on new Report Exporter features/requirements
    • Survey
    • Roles report
    • Associations report
ATOaas Updates

Discussion Points

  • March 24th is the target date for PROD.

Decision Points

Report Exporter Clearance

Discussion Points:

  • Question:"Web concept clearance process (OCPL and CBIIT)? This is required now before a new web domain is created. We probably shouldn't be using the nci.nih.gov domain anymore.”

  • The cloud PM asked if Sue if we completed the above process.
    • We did not as we started development before the process was implemented.

Decision Points:

  • Lyuba suggested that we follow the above process.
    • Jason will follow up with Sue.
Report Exporter

Discussion Points:

  • Deployed to Prod (behind firewall)
    • Initial testing/verification looks good.
  • AppScan on Prod: 1 Medium issue found
    • JQuery version needs to be updated to 3.6.0.
      • A fix is in on Dev for this.
      • We are requesting to move this fix to QA.
  • Work progressing on new feature requests
    • Survey
      • Who should be on the mailing list?
        • Lyuba, Lori
    • Roles report
    • Associations report
  • QA
    • Itendra agreed that we should proceed to deploy the jquery bugfix to QA for regression testing.

Decision Points:

Team Absences

Mayo Team

  • Cory - June 14th - 17th
  • Scott - May 13th - 18th
  • Craig - April 11 - May 7

NCI

  • Tracy -
  • Kumar -
  • Kim -

EVS SERVICE AND ARCHITECTURE GROUP UPDATES

EVS

Discussion Points:

Decision Points:

EVS Service and Architecture Group

Discussion Points:

Decision Points:


DATA UPDATES
Data

Discussion Points:

Decision Points:


BROWSER UPDATES

Browser

Discussion Points:

Decision Points: 

JIRA Issues

Recent LexEVS Related Bugs and Features (within last week)

Key Summary T Created Reporter P Status Affected Version/s Fix Version/s
Loading...
Refresh

Recent CTS2 Service Related Issues (within last week)

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

6.5 LexEVS Related Issues

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

6.5 CTS2 Service Related Issues

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh