Sprint Dates
-
Sprint Goals
- Identify new React library to support specs of the Data Model Navigator
- Begin DMN feature integrations
- Create microservice to create interoperability
- Complete design options for the File-Centric Cart page
- Enable JBrowse to open in a dedicated session window
- Implement node-expanding property counts in DMN Table View
- Support external links on the ICDC Spotlight page
Sprint Jira Issue Types
Completed in Sprint
Sprint Schedule
Date | Scrum Ceremony | Purpose |
---|---|---|
| Sprint Kickoff | Initiate new sprint |
| Sprint Pre-planning | Review tasks targeted for next sprint and identify clarifications needed, apply initial story point estimations and initial projected assignees |
| Sprint Planning | Review prioritized tasks, assert assigned stories, assert final story point estimations, review story points by assignee |
| Sprint Review & Retrospective | Demo work completed, discuss what went well and what can be improved |
Software Release Information
Date | Build Type | Jenkins Build | Front-End Version | Back-End Version | File System Version |
---|---|---|---|---|---|
| Internal Beta Release | 1024 | 3.44.0 | 14.5.1 | 1.4.0 |
| Internal Beta Release | 1025 | 3.44.1 | 14.5.1 | 1.4.0 |
| Internal Beta Release | 1028 | 3.45.0 | 14.5.1 | 1.4.0 |