NIH | National Cancer Institute | NCI Wiki  

Date

Attendees



Goals

Discussion items

TimeItemWhoNotes

Spring 5
  • Merge worked but still issues with multiple src directories
    • src/main/java vs /src/java
    • Tracy to summarize in email to Jason

System migration
  • Stage 2-
    • Per QA has instability.  Don't know if they are pursuing or we need to step in
    • Will ask about in next meeting

End of Life
  • Remote API and URI Resolver down on Dev and QA
    • Stage and Prod next week
  • CTS2 Service hopefully by Dec 2023
  • Spring 5 EOL December 2024
    • Spring 6 requires Java 17

Corretto
  • On Stage 2

SumoLogic to DataDog
  • Migration scheduled to begin in October and end in March 2024
  • Manish to set up a meeting to go over EVS migration and scheduling



ehcache
  • Nearing completion
  • ncitbrowser uses ehcache but need examination to see how complex the usage is.




Action items

  •