TimeItemWhoNotes

Spring 5
  • Merge worked but still issues with multiple src directories
    • src/main/java vs /src/java
    • Tracy to summarize in email to Jason
    • browser tagged and moved to QA. Tests passed

System migration
  • Stage 2-
    • Reported stability fixed with data deployment
    • Chuck waiting to transfer URLs until after the next data deployment
      • NCIt On Prod now
      • Monthlies by Monday
  • DataQA after Prod
    • database on machine - migrate first?
    • Test performance of old loaders vs new database.
    • Other apps follow DB - determine if needs to be co-located

End of Life
  • Remote API and URI Resolver down on Dev and QA
    • Stage and Prod next week
  • CTS2 Service - unlikely soon
  • Spring 5 EOL December 2024 - possibly commercial support
    • Spring 6 requires Java 17

Corretto
  • On Stage 2

SumoLogic to DataDog
  • Migration scheduled to begin in October and end in March 2024
  • Manish to set up a meeting to go over EVS migration and scheduling
    • experience migrating SL to DD?
    • Waiting on details of work scope
  • Notes from meeting with Manish:

ehcache
  • Nearing completion
  • ncitbrowser uses ehcache but need examination to see how complex the usage is.
  • Scott off for week and a half

Data release test scripts
  • Need to update scripts to work versus CTS2
  • Turn over to Chao and Eric
  • Submit to Systems