NIH | National Cancer Institute | NCI Wiki  

Document Information

Author: Craig Stancl, Scott Bauer, Cory Endle
Email: Stancl.craig@mayo.edu, bauer.scott@mayo.edu, endle.cory@mayo.edu
Team: LexEVS
Contract: S13-500 MOD4
Client: NCI CBIIT
National Institutes of Heath
US Department of Health and Human Services

Contents of this Page

Project Scope

The purpose of this document is to collect, analyze, and define high-level needs and features of the National Cancer Institute Center for LexEVS Release 6.3 and LexEVS Release 6.4. This document focuses on the functions proposed by the product stakeholders and target users in order to make it a better product.

6.3 will not be released as a production release.  It will be used as an internal development release for use by the NCI team only.  All features and fixes from 6.3 will be officially released as 6.4.  

Vision and Needs

The objective of this release of the LexEVS is to provide a bug fixes and a set of new features as captured in the document.

Functional Requirements

Each enhancement, modification or new feature is described in detail in the following documents.

LexEVS 6.3

Functional requirements for 6.3 can be found in the LexEVS 6.3 Scope Document.

LexEVS 6.4

Functional requirements for 6.4 can be found in the LexEVS 6.4 Scope Document.

Functional Bug Fixes

Each bug fix included in this release is described in detail in the following documents.  

LexEVS 6.3

Functional Bug Fixes for 6.3 can be found in the LexEVS 6.3 Scope Document.

LexEVS 6.4

Functional Bug Fixes for 6.4 can be found in the LexEVS 6.4 Scope Document.

Non-Functional Requirements

This section describes in detail all the related requirements which must be met for this release but do not add functionality. These requirements are included in the scope and project plan due to level of effort or relative importance to the overall success of delivery of the release.

Project

JIRA number (hyperlinked)

Project

Brief description of non-functional requirement

Status
(Approved or Proposed)

Iteration

LEXEVS-753 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Project Wiki SiteApproved6.3, 6.4
LEXEVS-751 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Project Management PlanApproved6.3, 6.4
LEXEVS-750 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Project Financial PlanApproved6.3, 6.4
LEXEVS-749 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Monthly Status ReportsApproved6.3, 6.4
LEXEVS-748 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Monthly Financial Status ReportApproved6.3, 6.4
LEXEVS-752 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Project Summary ReportApproved6.3, 6.4
LEXEVS-755 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Updated DocumentationApproved6.3, 6.4
LEXEVS-754 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Technical Project PlanApproved6.3, 6.4
LEXEVS-769 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Project Scope DocumentApproved6.3, 6.4
LEXEVS-756 - Getting issue details... STATUS LexEVSLexEVS 6.3 and 6.4 Weekly Meeting MinutesApproved6.3, 6.4

LexEVS 6.3

Non-Functional Requirements for 6.3 can be found in the LexEVS 6.3 Scope Document.

LexEVS 6.4

Non-Functional Requirements for 6.4 can be found in the LexEVS 6.4 Scope Document.

General Support Activities

This section describes in detail all the related activities which must be performed for this release but do not add functionality. These activities are included in the scope and project plan due to level of effort or relative importance to the overall success of delivery of the release.

JIRA number (hyperlinked)

Brief description of general support activity

Status
(Approved or Proposed)

Iteration

LEXEVS-766 - Getting issue details... STATUS

LexEVS 6.3 and 6.4 - Level 2 Support

Approved

6.3, 6.4


Out of Scope Items

Items that are out of scope were evaluated as part of the initial scoping activities for this release, and subsequently not included in the final approved scope. These items are also documented in the cumulative backlog of requirements found on the product JIRA site. They include out-of-scope functional requirements (enhancements or new features), bug fixes, non-functional requirements, and general support activities.

JIRA number (hyperlinked)

Project

Brief description of item moved from the in-scope section
with brief explanation added of why it was not included in this release

Iteration during which the item
was removed from in-scope