Attendees
Name | Role | Present |
---|---|---|
Wright, Larry | NIH/NCI | x |
Fragoso, Gilberto | NIH/NCI | x |
De Coronado, Sherri | NIH/NCI | |
Safran, Tracy | NIH/NCI | x |
Ong, Kim L | IS | |
Lucas, Jason R | IS | x |
Bauer, Scott | Mayo | x |
Stancl, Craig | Mayo | x |
Endle, Cory | Mayo | x |
Wynne, Robert | NIH/NCI | x |
Pan, JJ | NIH/NCI [E] | x |
Tran, Tin | NIH/NCI [C] | x |
Ahmed, Shamim | NIH/NC [C] | |
Haber, Margaret | (NIH/NCI) | |
Roth, Laura | (NIH/NLM) | |
Ramani, Vivek | (NIH/NCI) [C] | |
Carlsen, Brian | (NIH/NCI) [C] | |
Wong, Joanne | ||
Kuntipuram, Kumar | x |
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
64 | Scott | To follow up on URI's on OWL2 with Harold. | on hold | |||
156 | Scott | Scott to work with Gilberto to determine what is needed for OWL 2 requirements | 2014.04.30 | on hold | ||
164 | Cory | Cory to add implementation to CTS2 implementations page. | 2014.04.30 | on hold | ||
170 | Scott | Update the ARC dates to include range of dates for each tier. | 2014.05.14 | on hold | ||
185 | Gilberto | Create Jira for OWL 2 Annotation issue in the API. | 2014.05.28 | open | ||
197 | Scott | Do a gap analysis on what the URI_Resolver logs and what NCI would like to know from these logs | 2014.6.18 | on hold | ||
200 | Larry/Sherry | Query current LexEVS users about use of SOAP, REST or QBE services in the legacy caCORE api's | 2014.6.18 | open | ||
207 | Cory | Write issue against CTS2 OMG regarding the ability to return INACTIVE concepts only. | 2014.07.30 | open | ||
209 | Craig/Larry | Plan Techical F2F/AMIA meetings. | 2014.07.30 | on hold | ||
210 | Larry/Gilberto | Determine if there is a need to meet with the CTRP | 2014.07.30 | on hold | ||
212 | Larry | Include LexGrid XML Export as part of the 5.1 retirement notice. | 2014.07.30 | on hold | ||
218 | Scott/Cory | Provide QA date to Tin (Update Jira items for QA) | 2014.08.13 | open | ||
219 | Craig | Update plan to reflect the Sept 22 deployment week. | 2014.08.27 | done | ||
220 | Rob | Follow up on DNS entry requests | 2014.09.03 | open | ||
221 | Tin | Run the 508 compliance tool on http://ncias-d1224.nci.nih.gov:8080/lexevsapi62/ | 2014.09.03 | open | ||
222 | Scott | Provide deployment week plan to Jason and NCI team. | 2014.09.03 | open | ||
223 | Craig | Send updated project plan to group. | 2014.09.03 | open | ||
224 | Scott | URI Resolver - Provide overview of how to access the URI Resolver | 2014.09.03 | on hold | ||
225 | Scott | URI Resolver - Look at TLAMP and VSAC service to determine usage of URI Resolver | 2014.09.03 | on hold | ||
226 | Larry | Send reminder to group about NLM/CTS2 Demo and Discussion on Friday, Sept 5 | 2014.09.03 | open |
Progress
Immediate Priorities and Problems (Mayo Team) | Scott: JIRA LEXEVS-633, URIRESOLV-1
Cory: Working JIRA 599, 639
Craig: Project Plan Updates, Contract updates.
|
| |
caDSR and Value Set and other URIs (Weekly Status) | Nothing new. | ||
Dev DRT Security issues | Issues focused on not being able to resolved external XSDs. Scott requested security exceptions to allow access.
| ||
Miracle Week Support |
| ||
OWL (Gilberto) | Out of scope for 6.2 - no updates | ||
URI Resolver Discussion | Out of scope for 6.2 - need to have group review the JIRA item and provide feedback. Need to understand if can be externally exposed - or should be. When time, Scott will review what TLAMP and UMLS services use for a resolver. Would like to show how to query the URI directly. (code in Clojure) | ||
Landing page (If available) | Notes above. | ||
NLM Demo | NLM to show RDF representation of Mesh NLM direction, lessons learned. What was built for the demo - lessons learned, demo of client. Need to send out a reminder to the entire group (calendar invite) and ask about topics. - Larry | ||
QA Planning Discussion | Sept 10 - QA tier Sept 17 - Stage tier Goal to be on stage by Sept 26 (before Scott returns from DC). Artistic testing, junits can be run and user acceptance testing (starts on Dev) to be done on Stage. There may be differences when going from QA to Stage (network policy) Code freeze date on Sept 8 - Cory and Scott will check in code and create candidate. |
JIRA Issues
Description |
---|
LEXEVS-570 - Getting issue details... STATUS |
LEXEVS-573 - Getting issue details... STATUS |
LEXEVS-579 - Getting issue details... STATUS |
LEXEVS-586 - Getting issue details... STATUS |
LEXEVS-594 - Getting issue details... STATUS |
LEXEVS-597 - Getting issue details... STATUS |
LEXEVS-598 - Getting issue details... STATUS |
LEXEVS-599 - Getting issue details... STATUS |
LEXEVS-605 - Getting issue details... STATUS |
LEXEVS-606 - Getting issue details... STATUS |
LEXEVS-607 - Getting issue details... STATUS |
LEXEVS-608 - Getting issue details... STATUS |
LEXEVS-609 - Getting issue details... STATUS |
LEXEVS-612 - Getting issue details... STATUS |
LEXEVS-613 - Getting issue details... STATUS |
LEXEVS-615 - Getting issue details... STATUS |
LEXEVS-616 - Getting issue details... STATUS |
LEXEVS-617 - Getting issue details... STATUS |
LEXEVS-618 - Getting issue details... STATUS |
LEXEVS-619 - Getting issue details... STATUS |
LEXEVS-620 - Getting issue details... STATUS |
LEXEVS-621 - Getting issue details... STATUS |
LEXEVS-622 - Getting issue details... STATUS |
LEXEVS-623 - Getting issue details... STATUS |
LEXEVSCTS2-2 - Getting issue details... STATUS |
LEXEVSCTS2-3 - Getting issue details... STATUS |
Project Plan Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
None | ||||||
Planned Activities
Area of Interest | Details |
---|---|
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
Dependencies
Opened Date | Description | Assigned |
---|---|---|