Attendees
Name | Role | Present |
---|---|---|
Wright, Larry | NIH/NCI | x |
Fragoso, Gilberto | NIH/NCI | x |
De Coronado, Sherri | NIH/NCI | x |
Safran, Tracy | NIH/NCI | |
Ong, Kim L | IS | x |
Lucas, Jason R | IS | x |
Bauer, Scott | Mayo | x |
Stancl, Craig | Mayo | x |
Endle, Cory | Mayo | x |
Peterson, Kevin | Mayo | |
Wynne, Robert | NIH/NCI | x |
Pan, JJ | NIH/NCI [E] | x |
Tran, Tin | NIH/NCI [C] | x |
Carlsen, Brian | (NIH/NCI) [C] | |
Wong, Joanne | ||
Kuntipuram, Kumar | x |
Action Items
# | Assigned | Description | Date Identified | Due Date | Date Completed | Status |
---|---|---|---|---|---|---|
64 | Scott | To follow up on URI's on OWL2 with Harold. | on hold | |||
164 | Cory | Cory to add implementation to CTS2 implementations page. | 2014.04.30 | on hold | ||
185 | Gilberto | Create Jira for OWL 2 Annotation issue in the API. | 2014.05.28 | on hold | ||
197 | Scott | Do a gap analysis on what the URI_Resolver logs and what NCI would like to know from these logs | 2014.6.18 | on hold | ||
200 | Larry/Sherry | Query current LexEVS users about use of SOAP, REST or QBE services in the legacy caCORE api's | 2014.6.18 | on hold | ||
207 | Cory | Write issue against CTS2 OMG regarding the ability to return INACTIVE concepts only. | 2014.07.30 | on hold | ||
210 | Larry/Gilberto | Determine if there is a need to meet with the CTRP | 2014.07.30 | on hold | ||
212 | Larry | Include LexGrid XML Export as part of the 5.1 retirement notice. | 2014.07.30 | on hold | ||
224 | Scott | URI Resolver - Provide overview of how to access the URI Resolver | 2014.09.03 | on hold | ||
225 | Scott | URI Resolver - Look at TLAMP and VSAC service to determine usage of URI Resolver | 2014.09.03 | on hold | ||
235 | Mayo/NCI Team | Identify additional value set JIRA items to be included in 6.3 release. | 2014.10.02 | done | ||
237 | Scott | Final code deliverables posted to SFTP site and wiki pages updated. | 2014.10.02 | open | ||
244 | Craig | Plan meeting with Tracy to discuss collaborative LexEVS development process | 2014.12.03 | open | ||
245 | Kim/NCI | Confirm that the manifest and Tree Jar that Scott put on sftp will work. | 2014.12.10 | open | ||
246 | Cory | Investigate if possible to use Apache as a proxy for NodeJS | 2014.12.10 | open | ||
251 | Cory | Install NodeJS on NCI server. | 2014.12.17 | done | ||
251 | Craig | Update 6.3 project plan to include 6.2 release activities. | 2014.12.17 | done | ||
252 | Gilberto | Provide credentials to Cory for Protege server - to install Node.js and API doc tooling | 2015.01.07 | done | ||
253 | Scott | LexEVS 6.2 sftp site to be updated with 6.2 related Jars | 2015.01.07 | open | ||
254 | Tracy/Rob | EVS download page to be updated for 6.2. | 2015.01.07 | open | ||
255 | Scott | LexEVS 6.2 download page to be updated to point to the sftp site. | 2015.01.07 | open | ||
256 | Gilberto | Complete OWL 2 review by Wednesday, January 14 | 2015.01.07 | open | ||
257 | Scott | Meet with Gilberto to discuss OWL 2 duplicate relationships. | 2015.01.07 | open | ||
258 | NCI Team | Provide feedback on project plan. | 2015.01.07 | done | ||
259 | Scott/Cory | Verify that all distributed interfaces that are exposed are surfaced. | 2015.01.14 | open |
Progress
Immediate Priorities and Problems (Mayo Team) | Scott:
Cory:
Kevin:
Craig: Project Plan for 6.3 and 6.4
|
6.3 release planning, also 6.4 (Craig, Scott) | For the 6.3 release, the thought is that we may be able to deploy 6.3 to DEV. Then the TERMs Browser can test/develop with the namespace fix in 6.3.
|
Tree Evaluation – Feedback | Kim will need to provide feedback.
|
CTS2 API documentation | Discuss protege server deployment.
|
Shady Grove Deployment | Firewall exceptions have been completed.
|
Distributed API | Distributed interfaces - review all that are exposed are surfaced. (Include in 6.3 if possible) |
True Contains | Confirmed with Lucene instructor that functionality will be the same as before. Plan to review what exactly we are indexing and if we need to continue to do so. Also plan on reviewing all the search algorithms and decide if they are all still needed. |
JIRA Issues
Recent LexEVS Related Issues (within last week)
Recent CTS2 Service Related Issues (within last week)
6.3 LexEVS Related Issues
6.3 CTS2 Service Related Issues
Project Plan Changes
# | Description | Due Date | Resources | Notes | Risks | Mitigation |
---|---|---|---|---|---|---|
None | ||||||
Planned Activities
Area of Interest | Details |
---|---|
Risks, Issues, Dependencies
Risks
# | Opened Date | Due Date | Description | Likelihood (H, M, L) | Impact | Assigned | Status | Mitigation Strategy |
---|---|---|---|---|---|---|---|---|
Issues
# | Opened Date | Description | Impact | Assigned | Status |
---|---|---|---|---|---|
Dependencies
Opened Date | Description | Assigned |
---|---|---|