Attendees

NameRolePresent
Remennik, LyubovNIH/NCI

Safran, Tracy

NIH/NCI [C]
Ong, Kim LNIH/NCI [C]
Lucas, Jason RNIH/NCI [C]
Bauer, Scott  NIH/NCI [C]
Alkis, BarryNIH/NCI [C]
Solie, ChuckNIH/NCI [C]
Truong, TracyNIH/NCI [C]
Kondareddy, SwathiNIH/NCI [C]
Singh, ItendraNIH/NCI [C]
Zhang, ChaoNIH/NCI [C]
Johnson, ConnieNIH/NCI [C]
Whiteman, LoriNIH/NCI [C]
Benson, MarkNIH/NCI [C]

Agenda

EVS Discussion


SYSTEMS
Systems

Discussion Points: 

Decision Points: 


LEXEVS UPDATES

LexEVS Sprint Status


Current Sprint - Sprint 183 (March 24, 2021 – April 3, 2022)

16X237 Agile Development - Sprint Status#16X237AgileDevelopmentSprintStatus-Sprint183
  • Activities
    • Updates to Spring for LexEVS - working through the DAO and registry work
    • Noted Vulnerability now known to earlier Spring Version
LexEVS Spring Updates

Discussion Points:

  • Meeting to be scheduled with Denise?
    • No longer dependencies on caDSR app
    • There is a link from caDSR browser to old browser
  • Awareness of vulnerability
  • Completed several dao layers
  • Need to add Metathesaurus RRF, other formats for loading to scope
  • Still on schedule
  • OCPL relies on CTS2 - still trying to understand how they are using it
    • Reply arrived this morning
  • .Multiple teams - trying to identify which groups are using it and how

Decision Points:  

  • Agreed that CTS2 is the priority as remote is not used.
  • Jason mentioned Kim uses the remoteAPI to do development. Need to document changes that he will need to know
    • Kim asked for a link to the code branch we are working upon
  • Scott mentioned we would need to reload all of the data

CBIIT's enterprise github

Discussion Points:

  • Complete

Decision Points:

BOD 22-01 HHS Vulnerability Disclosure Link

Discussion Points:

  • Complete

Decision Points:

Meta Tree investigation

Discussion Points:

  • Nothing new to report

Decision Points:

CTS2 Mapping/URI Resolver

Discussion Points:

  • On Hold

Decision Points:

Statistics Dashboard

Discussion Points: 

  • Met with Manish and others
  • logs cannot be restored for the missing weeks of April and Months before that. 
  • We should now have at least 90 days of logs.  
  • Scheduled view was supposed to be the replacement.
  • Still no set of implementation instructions.

Decision Points:

2-prong effort:

  • Mark to communicate with group to explain our dependencies and the situation we have been placed in. Request a written response and the ID of the Federal person overseeing this.
  • Scott Put together a plan or description of the efforts we will go through to mitigate the issues going forward.
Comparison/Mapping Tool

Discussion Points

  • On Hold

Decision Points:

EVS transition to virtual machines

Discussion Points:

Decision Points:

Team Absences

Mayo Team

  • Scott - 
  • Tracy - Thursday AM this week


Vulnerability testing



EVS SERVICE AND ARCHITECTURE GROUP UPDATES

EVS Service and Architecture Group

Discussion Points:

Decision Points:


DATA UPDATES
Data

Discussion Points: New NCIt started May 31 (yesterday)

Decision Points:


BROWSER UPDATES

Browser

Discussion Points: No releases going through tiers currently

Decision Points: 


QA UPDATES

QA

Discussion Points: 

  • Finished EVSRestAPI and Explorer 1.6, being deployed to Stage
  • Data deployment to Stardog today 22.05e

Decision Points: 



TERMINOLOGIES LIFECYCLE REPORT

Terminology Updates and Schedule 

Discussion Points: 

Decision Points: 


LexEVS Spring Migration Progress


Spring Related Update

Estimated Effort

Status

Spring Related Update

Estimated Effort

Status

Ivy Dependency Update3 daysComplete
Ibatis to Mybatis xml conversion3 daysComplete
Compile capable code conversion3 daysComplete
Application context startup1 week Complete
CodingSchemeDao Verification tests / Code Corrections10 daysComplete
Association Dao Verification tests  / Code Corrections10 daysComplete
Registry Dao Verification  / Code Corrections10 daysComplete
Coded Node Graph Dao / Code Corrections10 daysIn progress
Entity Dao / Code Corrections10 daysComplete
NCI History Dao / Code Corrections3 daysComplete
Property Dao / Code Corrections10 daysComplete
Revision Dao / Code Corrections2 daysIn Progress
System Release Dao / Code Corrections1 dayIn Progress
Pick List Dao / Code Corrections1 week Not Started
Pick List Entry Dao / Code Corrections1 week Not Started
Source Asserted Value Set Dao / Code Corrections2 daysNot Started
Value Set Definitions Dao / Code Corrections10 daysNot Started
Value set Hierarchy Dao / Code Corrections1 day Not Started
Vaue set Definition Entry Dao / Code Corrections2 daysNot Started
Value Set Entry State Dao / Code Corrections2 daysNot Started
Value Set Property Dao / Code Corrections1 week Not Started
Versions Dao / Code Corrections2 days In Progress
Testing/ Verification1 week Not Started
Load tests 2 weeksNot Started
Testing verification Recoding10 daysNot Started
Full system test1 dayNot Started
LexEVS Remote3-4 weeksNot Started
LexEVS CTS2 Service2-3 weeksNot Started



Total Effort (Approximately)4-5 months

Vocabularies Slated for Production

 Terminology Updates and Schedule


Vocabulary Name

Local Name

Version

Arrival Date

Loaded to data-qa DB

Date to Stage

Date to Production

Vocabulary Name in LexBIG

Short Name

Version identifier

Date the vocabulary arrived for processing

Has the vocabulary been loaded to the data-qa database?

Approximate date the vocabulary version is scheduled to move to staging

Approximate date the vocabulary version is scheduled to move to production

SwissProtSwissProtMay202205/31/2022yes06/03/2206/06/22
NCIt-HGNCNCIt-HGNCMay202205/31/2022yes06/03/2206/06/22
NCI ThesaurusNCIt22.05e

 05/31/2022

yes06/03/2206/06/22
MED-RTMED-RTJun2022



HGNCHGNCJun22



GOGO




ChEBIChEBI





QA Schedule and Status

see QA Scheduling and Status

Section for upcoming releases ::

Application and Version

Scope of Release

DEV team’s estimate for Release Candidate Date

QA team’s estimated Time to Test per Iteration (Days)






Section for Functional System Testing Status ::

Application and Version

Percentage Complete

Estimated Completion Date per Iteration

Priority Level 

Type Of Testing

Current Tier for Release (DEV, QA, Stage, Prod)

Expected Production Date

EVS REST API (v1.6)

100%

5/27/2022

High

Progression + Regression 

QA


EVS Explore (v1.6)

100%

5/27/2022

High

Progression + Regression

QA


EVS REST API(v1.6)

20%

6/1/2022

High

Regression

Stage


EVS Explore(v1.6)

10%

6/2/2022

High

Regression

Stage


EVS REST API(22.05e) - Monthly Data Deployment


6/1/2022

High

Regression

Stage


EVS REST API(22.05e) - Monthly Data Deployment


6/1/2022

High

Regression

Production




JIRA Issues


Recent EVS Stats Dashboard Related Bugs and Features (within last week)

Key Summary T Created Reporter P Status
Loading...
Refresh

Recent Report Exporter Related Bugs and Features (within last week)

Key Summary T Created Reporter P Status
Loading...
Refresh

Recent LexEVS Related Bugs and Features (within last week)

Key Summary T Created Reporter P Status
Loading...
Refresh

Recent CTS2 Service Related Issues (within last week)

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

6.5 LexEVS Related Issues

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh

6.5 CTS2 Service Related Issues

Key Summary T Created Updated Due Assignee Reporter P Status Resolution
Loading...
Refresh